SITCOMTN-052
Provenance#
This document was generated based on the contents of the lsst-dm/milestones repository, version 774a35cc, dated 2025-07-07. This corresponds to the status recorded in the project controls system for May 2025. Download the report.csv here.
Summary#

Fig. 1 Current block schedule. Download the PDF of this Block Schedule here.#
The SITCOM Subsystem is currently tracking 252 milestones: 1 at Level 1, 2 at Level 2, 90 at Level 3, and 89 at Level 4. 70 have no level defined. Of these, 226 have been completed. Of the incomplete milestones, 15 are late relative to the baseline schedule, while the remainder are scheduled for the future.

Fig. 2 Milestone completion as a function of date.#

Fig. 3 SIT Milestone completion as a function of date.#

Fig. 4 COM Milestone completion as a function of date.#

Fig. 5 SUM Milestone completion as a function of date.#

Fig. 6 Telescope and Site Milestone completion as a function of date.#
Currently overdue milestones#
Overdue SIT milestones
SITCOM-101: EAS version 5 installed (main telescope) [Due 2020-01-02]
SITCOM-117: EAS fully integrated [Due 2022-03-31]
SITCOM-119: Ops rehearsal for data release processing #3 [Due 2025-05-29]
SITCOM-114: All Data Management 1a Priority Requirements Functionally Demonstrated [Due 2024-09-09]
SITCOM-116: Initial Optical testing on TMA complete [Due 2024-11-21]
SITCOM-121: System First Light with LSSTCam [Due 2025-05-29]
SITCOM-126: Engineering tests with LSSTCam complete [Due 2025-07-03]
Overdue COM milestones
COMC-0140: Start SV Data Collection [Due 2025-07-04]
COMC-3270: TMA AOS Ready [Due 2025-05-29]
COMC-3280: Rubin First Light [Due 2025-07-04]
COMC-060200-10500: Start of Science Verification Science Validations [Due 2025-07-04]
COMC-060200-20960: DMS Ready for Full system AI&T [Due 2025-05-29]
COMC-060204-1000: Operational lookup tables for AOS complete [Due 2025-06-19]
Overdue SUM milestones
SUMMIT-3077: COMP: LSSTCam Ready for Bulk Data Production [Due 2025-07-04]
SUMMIT-3082: COMP: LSSTCam-Tel Integration Complete [Due 2025-07-04]
Milestones by due date#
Due in September 2025#
COMC-2164: Commissioning Complete
COMC-3310: Rubin Eng Prep for OPS Start
COMC-3320: Rubin Operations Readiness Review
SITCOM-129: Science Verification Complete
COMC-0653-1000: COMP: Science Validation 1 Data Release Complete
COMC-0654-1000: COMP: Calibration Products Production Verified
COMC-0654-1070: COMP: Data Release Production Verified
COMC-0654-0430: COMP: Science Validation Surveys Complete
SITCOM-130: Operation Readiness Review Complete
Due in August 2025#
Due in July 2025#
COMC-1664: DMS Archive Center Complete at SLAC
COMC-0140: Start SV Data Collection
COMC-3280: Rubin First Light
COMC-060200-10500: Start of Science Verification Science Validations
COMC-0620-9000: Archive Center Ready for System I&T at SLAC
SUMMIT-3082: COMP: LSSTCam-Tel Integration Complete
SUMMIT-3077: COMP: LSSTCam Ready for Bulk Data Production
SITCOM-126: Engineering tests with LSSTCam complete
Due in June 2025#
COMC-060204-1000: Operational lookup tables for AOS complete
Due in May 2025#
COMC-3270: TMA AOS Ready
COMC-060200-10300: Start of On-Sky & Calibration Data with LSSTCam
COMC-060200-20960: DMS Ready for Full system AI&T
SITCOM-119: Ops rehearsal for data release processing #3
SITCOM-121: System First Light with LSSTCam
New1110: Full focal plane readout complete
New1165: Telescope Aligned
Due in April 2025#
COMC-0020: On-Sky Testing Begins w/Science Camera
COMC-0010: Camera In-Situ Calibration Begins
COMC-3250: Rubin First Photon
SITCOM-XXX: Camera Ready for Engineering Punchlist Resolution
SITCOM-122: LSSTCam Ready for On Sky (First Photon)
New1135: LSSTCam Cold
51: Ion Pumps On
66: CCDs on & Cryo Plate at Operating Temp
81: Ready for TMA Balancing
Due in March 2025#
Due in February 2025#
COMC-3230: LSSTCam on TMA
COMC-3240: TMA Aligned
SITCOM-115: SIT-Com activities with ComCam Complete
SITCOM-123: LSSTCam Installed on TMA
Due in January 2025#
Due in December 2024#
Due in November 2024#
COMC-3260: TMA Pointing Models Complete
SITCOM-116: Initial Optical testing on TMA complete
Due in October 2024#
SUMMIT-Oct24-170: START: ComCam First Photon
COMC-0642-9999: COMP: DMS- Integration Complete
Due in September 2024#
COMC-3140: ComCam Installed on TMA
COMC-3160: ComCam First Photon
SITCOM-111: In-Dome Calibration Hardware Ready for On-Sky Operations
SUMMIT-Oct24-160: ComCam Reinstalled on TMA
SITCOM-114: All Data Management 1a Priority Requirements Functionally Demonstrated
Due in August 2024#
COMC-060200-10210: Start of LSSTCam re-Verification
COMC-060200-20770: Global Interlock System Ready
SUMMIT-Oct24-150: START: Reinstall ComCam on TMA
Due in July 2024#
No milestones due.
Due in June 2024#
COMC-3150: M1M3 Glass on TMA
SITCOM-110: M1M3 installed on the TMA
Due in May 2024#
COMC-3130: M2 Glass on TMA
COMC-3210: LSSTCam on Top End Assembly
COMC-NR-701100(110): Camera And Equipment at SFO
COMC-NR-701600(111): LSST Camera at Santiago Airport
COMC-NR-720000(075): L1-L2 Container Ready for Shipping
COMC-NR-720100(082): Shutter Equipment Ready for Shipping
COMC-NR-720200(87): FES Support Hardware Ready for Shipping
COMC-NR-606530(30): Shutter #2 Ready for Shipping
COMC-NR-606590(45): Filters Ready for Shipping
COMC-NR-606620(58): Cryo Cabinets Ready for Shipping
COMC-NR-606650(65): Chiller #1 Ready for Shipping
COMC-060200-20970: Ready to Start Full System AI&T
SITCOM-109: M1M3 Mirror Coating completed
Due in April 2024#
COMC-0130: Camera Ready for System Integration
COMC-0620-2150: Start Summit Commissioning Cluster Test & Verification
COMC-3110: M2 Cell Removed from TMA
COMC-3120: M2 Glass Installed
COMC-3200: LSSTCam Reverification End
COMC-NR-606560(36): Filter Exchange Spares Ready for Shipping
COMC-060200-20930: Camera Ready for Full System AI&T
SITCOM-127: M2 coating decision
SITCOM-104: M2 Glass installed on Cell
SUMMIT-3056: COMP: Camera Reverification Complete
SITCOM-125: LSSTCam reverification complete
Due in March 2024#
Due in February 2024#
Due in January 2024#
Due in December 2023#
SUMMIT-3023: COMP: TMA Refrigeration Tests Complete
Due in November 2023#
SITCOM-124: Camera Arrives at Summit Facility
COMC-0120: Camera Arrives at Summit Facility
SUMMIT-2976: LSSTCam Received @ Summit
COMC-0620-6500: Camera Received @ Summit
SUMMIT-3055: COMP: L1/L2 recevied at summit
Due in October 2023#
COMC-0005: Pre-Ship Camera Accepted
SUMMIT-2975: LSSTCam Pre-Ship Acceptance
COMC-NR-700500(066): Camera Spares Ready for Shipping
COMC-0620-6300: Camera Pre-Ship Acceptance
COMC-0620-0940: Mirror Integration Complete
SITCOM-105: ComCam + PF re-Installed on TMA
Due in September 2023#
COMC-3080: LSSTCam Pack and Transport
COMC-NR-700000(023): Camera Ready for Shipping
COMC-NR-700600(100): Camera Support Hardware & Fixtures Ready for Shipping
COMC-NR-606380(17): NEED: Hillman Rollers and Procedure
SITCOM-103: M2 fit check successful
Due in August 2023#
COMC-2264: Calibration Telescope Ready for Operations
COMC-3020: Pathfinder Testing starts
SITCOM-97: M1M3 cell+Surrogate Dynamic Testing on TMA done
SUMMIT-2990: COMP: Calibration Telescope Ready for Operations
SITCOM-120: Calibration Pipeline fully implemented
SITCOM-118: AuxTel ready for on-sky characterisation
Due in July 2023#
SITCOM-92: Camera support asmy w/ComCam+PF+Int#1+CCW Installed on Telescope
SITCOM-102: TMA safe for transition to M1M3 glass mirror
SITCOM-99: M1M3 cell + surrogate installed and verified on the TMA
COMC-060200-20800: Telescope 3-Mirror Testing Starts
SUMMIT-3013: NEED: Pathfinder in ComCam on TMA
Due in June 2023#
COMC-3050: TMA Final Testing Complete
SITCOM-106: Initial integrated tests on TMA complete
SITCOM-98: T&S Milestone: TMA Contract Complete
Due in May 2023#
COMC-0030: Start Early Integration and Test
COMC-0864: Telescope Top End Interface Ready for ComCam Integration
COMC-1064: ComCam Ready at Summit
COMC-1464: Start Photometric Calibration Tests
COMC-0620-0800: Start In-Situ TMA Testing
COMC-06020200-0800: Start Commissioning Readiness Review Preparations
COMC-NR-606290(12): Shipping Frame Ready for Camera
COMC-0620-2240: Base-Archive Network Full BW (100 Gbps)
Due in April 2023#
SITCOM-108: Level-3 is ready for the M1M3 surrogate to glass transition
SITCOM-100: M1M3 cell + Surrogate ready for installation on the TMA
Due in March 2023#
No milestones due.
Due in February 2023#
No milestones due.
Due in January 2023#
No milestones due.
Due in December 2022#
No milestones due.
Due in November 2022#
No milestones due.
Due in October 2022#
No milestones due.
Due in September 2022#
No milestones due.
Due in August 2022#
No milestones due.
Due in July 2022#
SITCOM-94: Level 3 System Spread integrations activities done
SUMMIT-2983: COMP: ComCam re-Verification Complete
Due in June 2022#
COMC-060200-20700: TMA Final Tests Start
COMC-0620-1100: Telescope Approved for System I&T
COMC-0620-0840: TMA Pre-Commissioning Acceptance
Due in May 2022#
COMC-060200-20965: Early System AI&T Complete
SITCOM-96: Computing Infrastructure in Place
SITCOM-112: Commissioning Compute Cluster fully configured and ready for general SIT-Com use
Due in April 2022#
No milestones due.
Due in March 2022#
SITCOM-117: EAS fully integrated
SITCOM-95: Level 7th ready to receive the Camera cart Assembly
Due in February 2022#
SUMMIT-2955-500: Ready for ComCam - Refrigeration Tubing
Due in January 2022#
No milestones due.
Due in December 2021#
SITCOM-90: ComCam + PF ready for on cart installation
Due in November 2021#
No milestones due.
Due in October 2021#
COMC-060200-20760: TCS w/WFS Available on Summit
Due in September 2021#
SUMMIT-3010: NEED: Access to TMA Refrigeration Lines
Due in August 2021#
SITCOM-91: Camera cart is fully assembled and tested
Due in July 2021#
No milestones due.
Due in June 2021#
No milestones due.
Due in May 2021#
No milestones due.
Due in April 2021#
No milestones due.
Due in March 2021#
COMC-2864: ComCam Ready for Onsite Systems Test
Due in February 2021#
No milestones due.
Due in January 2021#
No milestones due.
Due in December 2020#
COMC-0028: Base - Archive Network Verified
COMC-0620-2065: Base - Archive Network Functional 100 Gbps
Due in November 2020#
No milestones due.
Due in October 2020#
No milestones due.
Due in September 2020#
No milestones due.
Due in August 2020#
SITCOM-88: Camera cart ready for ComCam
Due in July 2020#
NCSA-000: Start NCSA FY20 Services
Due in June 2020#
COMC-060200-20920: TMA Ready to Start Early System AI&T
SITCOM-89: ComCam + PathFinder installed on the cart Assembly at Level 3
Due in May 2020#
COMC-0964: Start ComCam Integration on Summit
COMC-1564: DMS Base Center Complete
COMC-060200-20750: ComCam arrives at summit
COMC-0620-0020: DMS Base Center Approved for System I&T
COMC-0620-2080: Summit Commissioning Cluster Test & Verficiation
COMC-0620-2090: Com. Cluster R8.1 Pre-Commissioning Acceptance
Due in April 2020#
SUMMIT-2965: COMP: Camera Summit facility Ready for Use
COMC-060200-10000: Start of On-Sky Data from Auxiliary Telescope
Due in March 2020#
A5860: Start of Tucson Integration Tests w/ComCam
COMC-060202-50750: COMP: C_FDR - Transport Container
SUMMIT-3008: AVAIL: White Room Refrigeration System Ready for LSSTCam
SUMMIT-3009: AVAIL: Pathfinder for ComCam
Due in February 2020#
COMC-1164: Commissioning Data Processing Cluster Ready for ComCam Use
Due in January 2020#
COMC-060200-20780: Auxiliary Telescope + Spectrograph Ready
SITCOM-101: EAS version 5 installed (main telescope)
Due in December 2019#
No milestones due.
Due in November 2019#
COMC-06020200-1100: Commissioning Readiness Review Complete
SUMMIT-2993: NEED: Refrigeration Pathfinder on summit
Due in October 2019#
COMC-060200-20810: Camera Cart1 + Integrator1 + CCW ready for ComCam
Due in September 2019#
SIM-M2: UW Team FY19 Year End
COMC-060202-50450: COMP: C_FDR - Transport Container
COMC-060202-21110: Camera Hexapod/Rotator Ready for Integration
Due in August 2019#
COMC-060200-20030: Dome Installation Substantial Completion
Due in July 2019#
COMC-0564: ComCam Ready for System Tests
COMC-2464: ComCam Ready for Verification in Tucson
COMC-0620-3900: Shutter Pre-Integration Acceptance
SUMMIT-2994: NEED: MIE Chile (TMA) Compressors
Due in June 2019#
COMC-0620-0900: Start Mirror Coating & Integration
COMC-0620-4400: Start L1L2 Testing & Verification
COMC-06020201-1000: MIE: NEED: Filter Changer in Tucson
SITCOM-93: EAS Version 3 (construction tracking) ready to start
Due in May 2019#
COMC-0021: Mountain-Base Network Verified
COMC-0620-2000: Start Base Facility Inspection
COMC-0620-4100: Start Integrated Cryostat Testing
COMC-060200-20050: Summit Facility Camera Utility Room Ready
COMC-060200-20500: Summit Facility Clean Room Ready
COMC-060200-20400: Camera Staging Area Utilities Ready
COMC-060200-20200: Camera Facility Refrigeration Lines Ready
COMC-060200-20300: Summit Facility White Room ready
Due in April 2019#
COMC-0364: ComCam Dewar Assmebly Ready for Integration
COMC-2364: Coating Facility Ready for Operations
COMC-0620-3000: Start Filter Mechanism Testing
COMC-0620-3700: Start Shutter Testing
COMC-060200-20505: ComCam Dewar & Imaging System Ready for AI&T at Slac
COMC-0620-0540: TS M1M3 Pre-Ship Acceptance
Due in March 2019#
COMC-0620-3400: Start L3 Assembly Test
COMC-0620-3600: L3 Pre-Ship Acceptance
COMC-0620-4600: L1L2 Pre-Ship Acceptance
Due in February 2019#
SUMMIT-2992: AVAIL: Refrigeration Pathfinder to ship
Due in January 2019#
COMC-0620-3200: Filter Mechanism Pre-Ship Acceptance
COMC-0620-4700: Full Filter Complement Acceptance
Due in December 2018#
COMC-060202-50200: COMP: C_PDR - Transport Container
Due in November 2018#
COMC-0620-0500: Start M1M3+Cell Integration at SOML
COMC-060200-20100: Camera Facility Fiber Optic Lines Ready
COMC-060200-20520: Base Facility Data Center Building + Utilities Ready
COMC-0620-2040: Base Facility Inspection Complete
COMC-0620-4000: Corner Rafts Pre-Ship Acceptance
COMC-0620-4300: Cryostat+FPA Pre-Integration Acceptance
COMC-060203-30028: COMP: C_FDR - Pathfinder
Due in October 2018#
COMC-0620-0300: Start M2+Cell Integrated Optical Tests
COMC-06020201-2200: MIE: PSR ComCam deliverables
COMC-060200-20510: ComCam Dewar Ready for AI&T in Tucson
COMC-060200-20710: OCS Available on Summit
Due in September 2018#
SIM-M1: UW Sims FY18 Year End
COMC-0620-2070: Base Infrastructure Pre-Ship Acceptance
Due in August 2018#
COMC-060200-20020: Summit Control Room Available
COMC-060200-20025: Engineering Facility Database Functional
COMC-0620-0640: Coating Chamber Pre-Ship Acceptance
Due in July 2018#
COMC-0464: ComCam Optics & Filters Ready for Integration in tucson
COMC-060203-30018: COMP: C_PDR - Pathfinder
Due in June 2018#
COMC-0620-0600: Start Coating System testing at Vendor
COMC-060200-20010: Summit Facility Computer Room Available
Due in May 2018#
COMC-06020201-3180: COMP: C_CR - 2018 Commissioning Review
COMC-0620-0340: M2 Pre-Ship Acceptance
Due in April 2018#
COMC-060200-20000: Summit Network Available
COMC-060203-30008: COMP: C_CDR - Pathfinder
Due in March 2018#
COMC-06020201-3100: COMP: C_TCR - 2018 Technical Commissioning Review
COMC-0620-2050: MTN-Base Network Full BW (2 x 100 Gbps)
Due in February 2018#
COMC-0620-0700: Start Summit Facility Inspection
COMC-0620-0240: Rotator/Hexapopd Pre-Ship Acceptance
Due in January 2018#
COMC-0620-3300: 1st Production Science Raft Acceptance
Due in December 2017#
COMC-0620-0440: TMA Pre-Ship Acceptance
Due in November 2017#
COMC-0620-0740: Summit Facility Inspection Complete
Due in October 2017#
No milestones due.
Due in September 2017#
No milestones due.
Due in August 2017#
No milestones due.
Due in July 2017#
No milestones due.
Due in June 2017#
COMC-0620-0200: Start Rotator/Hexapod Testing at Vendor
COMC-06020201-1200: MIE: NEED: Shutter at SLAC
Due in May 2017#
No milestones due.
Due in April 2017#
COMC-06020200-0700: Commissioning Baseline Accepted
Due in March 2017#
No milestones due.
Due in February 2017#
No milestones due.
Due in January 2017#
COMC-06020200-0500: Commissioning PDR Complete
Due in December 2016#
No milestones due.
Due in November 2016#
COMC-0620-0400: Start TMA Test at Vendor
Due in October 2016#
No milestones due.
Due in September 2016#
No milestones due.
Due in August 2016#
No milestones due.
Due in July 2016#
No milestones due.
Due in June 2016#
COMC-0620-0100: Start Dome Testing at Vendor
Due in May 2016#
No milestones due.
Due in April 2016#
No milestones due.
Due in March 2016#
No milestones due.
Due in February 2016#
No milestones due.
Due in January 2016#
No milestones due.
Due in December 2015#
No milestones due.
Due in November 2015#
No milestones due.
Due in October 2015#
No milestones due.
Due in September 2015#
Due in August 2015#
No milestones due.
Due in July 2015#
No milestones due.
Due in June 2015#
COMC-2310: LSE-76 Infrastructure between Summit Fac. & DM - Phase 3, DM Milestone
Due in May 2015#
No milestones due.
Due in April 2015#
No milestones due.
Due in March 2015#
No milestones due.
Due in February 2015#
No milestones due.
Due in January 2015#
COMC-1205: LSE-140 Aux Instrum ICD between DM & T&S, Phase 3, DM Milestone
Milestones by WBS#
06C.00: SITCOM Management Level 2 Milestones#

Fig. 7 Relationships between milestones in WBS 06C.00 and their immediate predecessors and successors. Ellipses correspond to milestones within this WBS element; rectangles to those in other elements. Blue milestones have been completed; orange milestones are overdue.#
COMC-1205: LSE-140 Aux Instrum ICD between DM & T&S, Phase 3, DM Milestone#
Level: 3
Due: 2015-01-13
Completed: 2019-07-31
Warning
No description available
COMC-2310: LSE-76 Infrastructure between Summit Fac. & DM - Phase 3, DM Milestone#
Level: 3
Due: 2015-06-02
Completed: 2019-07-31
Warning
No description available
COMC-2330: LSE-76 Infrastructure between Summit Fac. & DM - Phase 3, T&S Milestone#
Level: 3
Due: 2015-09-02
Completed: 2017-09-30
Warning
No description available
COMC-1110: LSE-132 Infrastructure between Summit Fac. & OCS - Phase 3, T&S Milestone#
Level: 3
Due: 2015-09-02
Completed: 2019-04-15
Warning
No description available
COMC-0620-0100: Start Dome Testing at Vendor#
Level: 3
Due: 2016-06-06
Completed: 2016-06-06
Warning
No description available
COMC-0620-0400: Start TMA Test at Vendor#
Level: 3
Due: 2016-11-01
Completed: 2016-11-01
Warning
No description available
COMC-0620-0200: Start Rotator/Hexapod Testing at Vendor#
Level: 3
Due: 2017-06-28
Completed: 2017-06-28
Warning
No description available
COMC-0620-0700: Start Summit Facility Inspection#
Level: 3
Due: 2018-02-28
Completed: 2018-02-28
Warning
No description available
COMC-0620-0600: Start Coating System testing at Vendor#
Level: 3
Due: 2018-06-11
Completed: 2018-06-11
Warning
No description available
COMC-0620-0300: Start M2+Cell Integrated Optical Tests#
Level: 3
Due: 2018-10-01
Completed: 2018-10-01
Warning
No description available
COMC-0620-0500: Start M1M3+Cell Integration at SOML#
Level: 3
Due: 2018-11-15
Completed: 2018-11-15
Warning
No description available
COMC-0620-3400: Start L3 Assembly Test#
Level: 3
Due: 2019-03-11
Completed: 2019-03-11
Warning
No description available
COMC-0364: ComCam Dewar Assmebly Ready for Integration#
Level: 3
Due: 2019-04-09
Completed: 2019-06-01
Warning
No description available
COMC-0620-3000: Start Filter Mechanism Testing#
Level: 3
Due: 2019-04-12
Completed: 2019-04-12
Warning
No description available
COMC-0620-3700: Start Shutter Testing#
Level: 3
Due: 2019-04-19
Completed: 2019-04-19
Warning
No description available
COMC-2364: Coating Facility Ready for Operations#
Level: 3
Due: 2019-04-24
Completed: 2019-06-03
Warning
No description available
COMC-0620-4100: Start Integrated Cryostat Testing#
Level: 3
Due: 2019-05-01
Completed: 2019-05-01
Warning
No description available
COMC-0620-2000: Start Base Facility Inspection#
Level: 3
Due: 2019-05-03
Completed: 2019-05-03
Warning
No description available
COMC-0021: Mountain-Base Network Verified#
Level: 3
Due: 2019-05-10
Completed: 2019-05-10
Warning
No description available
COMC-0620-0900: Start Mirror Coating & Integration#
Level: 3
Due: 2019-06-03
Completed: 2019-06-03
Warning
No description available
COMC-0620-4400: Start L1L2 Testing & Verification#
Level: 3
Due: 2019-06-12
Completed: 2019-06-12
Warning
No description available
COMC-2464: ComCam Ready for Verification in Tucson#
Level: 3
Due: 2019-07-01
Completed: 2019-07-01
Warning
No description available
COMC-0564: ComCam Ready for System Tests#
Level: 3
Due: 2019-07-18
Completed: 2019-07-31
Warning
No description available
COMC-1164: Commissioning Data Processing Cluster Ready for ComCam Use#
Level: 3
Due: 2020-02-28
Completed: 2020-02-28
Warning
No description available
A5860: Start of Tucson Integration Tests w/ComCam#
Level: 4
Due: 2020-03-31
Completed: 2020-03-31
Warning
No description available
COMC-0964: Start ComCam Integration on Summit#
Level: 3
Due: 2020-05-13
Completed: 2021-03-31
Warning
No description available
COMC-1564: DMS Base Center Complete#
Level: 3
Due: 2020-05-13
Completed: 2020-02-28
Warning
No description available
COMC-0028: Base - Archive Network Verified#
Level: 3
Due: 2020-12-29
Completed: 2023-09-20
Warning
No description available
COMC-2864: ComCam Ready for Onsite Systems Test#
Level: 3
Due: 2021-03-31
Completed: 2021-03-31
Warning
No description available
COMC-0030: Start Early Integration and Test#
Level: 3
Due: 2023-05-01
Completed: 2023-05-01
Warning
No description available
COMC-0864: Telescope Top End Interface Ready for ComCam Integration#
Level: 3
Due: 2023-05-01
Completed: 2023-05-01
Warning
No description available
COMC-1064: ComCam Ready at Summit#
Level: 3
Due: 2023-05-01
Completed: 2023-05-01
Warning
No description available
COMC-1464: Start Photometric Calibration Tests#
Level: 3
Due: 2023-05-01
Completed: 2023-05-01
Warning
No description available
COMC-0620-0800: Start In-Situ TMA Testing#
Level: 3
Due: 2023-05-01
Completed: 2023-05-01
Warning
No description available
COMC-3050: TMA Final Testing Complete#
Level: Undefined
Due: 2023-06-19
Completed: 2024-04-25
Warning
No description available
COMC-3020: Pathfinder Testing starts#
Level: Undefined
Due: 2023-08-11
Completed: 2024-02-19
Warning
No description available
COMC-2264: Calibration Telescope Ready for Operations#
Level: 3
Due: 2023-08-31
Completed: 2024-10-01
Warning
No description available
COMC-3080: LSSTCam Pack and Transport#
Level: Undefined
Due: 2023-09-06
Completed: 2024-05-10
Warning
No description available
COMC-0005: Pre-Ship Camera Accepted#
Level: 3
Due: 2023-10-20
Completed: 2024-04-09
Warning
No description available
SITCOM-124: Camera Arrives at Summit Facility#
Level: 4
Due: 2023-11-14
Completed: 2024-05-16
Warning
No description available
COMC-0120: Camera Arrives at Summit Facility#
Level: Undefined
Due: 2023-11-14
Completed: 2024-05-16
Warning
No description available
COMC-3000: TMA Final Testing Begins#
Level: Undefined
Due: 2024-01-03
Completed: 2024-02-08
Warning
No description available
COMC-3010: M1M3 Lift Test#
Level: Undefined
Due: 2024-01-08
Completed: 2024-02-02
Warning
No description available
COMC-3030: M1M3 Glass Lift Prep#
Level: Undefined
Due: 2024-01-24
Completed: 2024-02-16
Warning
No description available
COMC-3170: LSSTCam Reverification Start#
Level: Undefined
Due: 2024-02-08
Completed: 2024-08-15
Warning
No description available
COMC-3040: M1M3 Glass Installed#
Level: Undefined
Due: 2024-02-13
Completed: 2024-03-20
Warning
No description available
COMC-3220: LSSTCam L3 Checkout Done#
Level: Undefined
Due: 2024-02-22
Completed: 2024-12-02
Warning
No description available
COMC-3070: ComCam Removed from TMA#
Level: Undefined
Due: 2024-03-04
Completed: 2024-05-24
Warning
No description available
COMC-3060: M1M3 Coating Begins#
Level: Undefined
Due: 2024-03-11
Completed: 2024-04-29
Warning
No description available
COMC-3090: LSSTCam Arrival Allowed#
Level: Undefined
Due: 2024-03-12
Completed: 2024-04-29
Warning
No description available
COMC-0620-2150: Start Summit Commissioning Cluster Test & Verification#
Level: 3
Due: 2024-04-15
Completed: 2024-04-15
Warning
No description available
COMC-3110: M2 Cell Removed from TMA#
Level: Undefined
Due: 2024-04-16
Completed: 2024-06-20
Warning
No description available
COMC-3120: M2 Glass Installed#
Level: Undefined
Due: 2024-04-25
Completed: 2024-07-10
Warning
No description available
COMC-0130: Camera Ready for System Integration#
Level: 3
Due: 2024-04-30
Completed: 2024-12-06
Warning
No description available
COMC-3200: LSSTCam Reverification End#
Level: Undefined
Due: 2024-04-30
Completed: 2024-12-06
Warning
No description available
COMC-3210: LSSTCam on Top End Assembly#
Level: Undefined
Due: 2024-05-14
Completed: 2025-02-05
Warning
No description available
COMC-3130: M2 Glass on TMA#
Level: Undefined
Due: 2024-05-21
Completed: 2024-07-25
Warning
No description available
COMC-3150: M1M3 Glass on TMA#
Level: Undefined
Due: 2024-06-12
Completed: 2024-10-04
Warning
No description available
COMC-3140: ComCam Installed on TMA#
Level: Undefined
Due: 2024-09-06
Completed: 2024-08-19
Warning
No description available
COMC-3160: ComCam First Photon#
Level: Undefined
Due: 2024-09-09
Completed: 2024-10-04
Warning
No description available
COMC-3260: TMA Pointing Models Complete#
Level: Undefined
Due: 2024-11-14
Completed: 2025-04-30
Warning
No description available
COMC-3180: ComCam off Sky#
Level: Undefined
Due: 2024-12-12
Completed: 2024-12-12
Warning
No description available
COMC-3190: ComCam off TMA#
Level: Undefined
Due: 2024-12-19
Completed: 2024-12-20
Warning
No description available
COMC-0240: Begin Full system Integration#
Level: 3
Due: 2025-01-06
Completed: 2025-01-06
Warning
No description available
COMC-3230: LSSTCam on TMA#
Level: Undefined
Due: 2025-02-19
Completed: 2025-03-06
Warning
No description available
COMC-3240: TMA Aligned#
Level: Undefined
Due: 2025-02-26
Completed: 2025-04-14
Warning
No description available
COMC-0020: On-Sky Testing Begins w/Science Camera#
Level: 3
Due: 2025-04-15
Completed: 2025-04-15
Warning
No description available
COMC-0010: Camera In-Situ Calibration Begins#
Level: 3
Due: 2025-04-17
Completed: 2025-04-17
Warning
No description available
COMC-3250: Rubin First Photon#
Level: Undefined
Due: 2025-04-22
Completed: 2025-04-15
Warning
No description available
COMC-3270: TMA AOS Ready#
Level: Undefined
Due: 2025-05-29
Completion pending
Warning
No description available
COMC-1664: DMS Archive Center Complete at SLAC#
Level: 3
Due: 2025-07-04
Completed: 2025-04-30
Warning
No description available
COMC-0140: Start SV Data Collection#
Level: 3
Due: 2025-07-04
Completion pending
Warning
No description available
COMC-3280: Rubin First Light#
Level: Undefined
Due: 2025-07-04
Completion pending
Warning
No description available
COMC-3290: Rubin SV1 Start#
Level: Undefined
Due: 2025-08-15
Completion pending
Warning
No description available
COMC-3300: Rubin SV2 Start#
Level: Undefined
Due: 2025-08-15
Completion pending
Warning
No description available
COMC-3310: Rubin Eng Prep for OPS Start#
Level: Undefined
Due: 2025-09-11
Completion pending
Warning
No description available
COMC-2164: Commissioning Complete#
Level: 3
Due: 2025-09-18
Completion pending
Warning
No description available
COMC-3320: Rubin Operations Readiness Review#
Level: Undefined
Due: 2025-09-18
Completion pending
Warning
No description available
06C.02: Commissioning#

Fig. 8 Relationships between milestones in WBS 06C.02 and their immediate predecessors and successors. Ellipses correspond to milestones within this WBS element; rectangles to those in other elements. Blue milestones have been completed; orange milestones are overdue.#
COMC-06020200-0500: Commissioning PDR Complete#
Level: 4
Due: 2017-01-27
Completed: 2017-01-27
Warning
No description available
COMC-06020200-0700: Commissioning Baseline Accepted#
Level: 4
Due: 2017-04-14
Completed: 2017-12-01
Warning
No description available
COMC-06020201-1200: MIE: NEED: Shutter at SLAC#
Level: Undefined
Due: 2017-06-10
Completed: 2017-06-10
Warning
No description available
COMC-0620-0740: Summit Facility Inspection Complete#
Level: 3
Due: 2017-11-13
Completed: 2019-01-01
Warning
No description available
COMC-0620-0440: TMA Pre-Ship Acceptance#
Level: 3
Due: 2017-12-01
Completed: 2018-11-19
Warning
No description available
COMC-0620-3300: 1st Production Science Raft Acceptance#
Level: 3
Due: 2018-01-12
Completed: 2017-05-26
Warning
No description available
COMC-0620-0240: Rotator/Hexapopd Pre-Ship Acceptance#
Level: 3
Due: 2018-02-21
Completed: 2019-01-01
Warning
No description available
COMC-06020201-3100: COMP: C_TCR - 2018 Technical Commissioning Review#
Level: 3
Due: 2018-03-05
Completed: 2018-02-01
Warning
No description available
COMC-0620-2050: MTN-Base Network Full BW (2 x 100 Gbps)#
Level: 3
Due: 2018-03-27
Completed: 2018-04-02
Warning
No description available
COMC-060200-20000: Summit Network Available#
Level: 4
Due: 2018-04-12
Completed: 2018-10-01
Warning
No description available
COMC-060203-30008: COMP: C_CDR - Pathfinder#
Level: 4
Due: 2018-04-19
Completed: 2018-01-18
Warning
No description available
COMC-06020201-3180: COMP: C_CR - 2018 Commissioning Review#
Level: 3
Due: 2018-05-07
Completed: 2018-07-31
Warning
No description available
COMC-0620-0340: M2 Pre-Ship Acceptance#
Level: 3
Due: 2018-05-11
Completed: 2018-10-31
Warning
No description available
COMC-060200-20010: Summit Facility Computer Room Available#
Level: 4
Due: 2018-06-07
Completed: 2018-10-01
Warning
No description available
COMC-0464: ComCam Optics & Filters Ready for Integration in tucson#
Level: 1
Due: 2018-07-09
Completed: 2019-02-01
Warning
No description available
COMC-060203-30018: COMP: C_PDR - Pathfinder#
Level: 4
Due: 2018-07-30
Completed: 2018-07-31
Warning
No description available
COMC-060200-20025: Engineering Facility Database Functional#
Level: 4
Due: 2018-08-06
Completed: 2018-11-04
Warning
No description available
COMC-0620-0640: Coating Chamber Pre-Ship Acceptance#
Level: 3
Due: 2018-08-13
Completed: 2018-08-14
Warning
No description available
COMC-060200-20020: Summit Control Room Available#
Level: 4
Due: 2018-08-20
Completed: 2018-10-01
Warning
No description available
COMC-0620-2070: Base Infrastructure Pre-Ship Acceptance#
Level: 3
Due: 2018-09-26
Completed: 2018-04-11
Warning
No description available
SIM-M1: UW Sims FY18 Year End#
Level: 4
Due: 2018-09-28
Completed: 2018-10-01
Warning
No description available
COMC-06020201-2200: MIE: PSR ComCam deliverables#
Level: Undefined
Due: 2018-10-01
Completed: 2019-05-31
Warning
No description available
COMC-060200-20710: OCS Available on Summit#
Level: 4
Due: 2018-10-12
Completed: 2019-11-09
Warning
No description available
COMC-060200-20510: ComCam Dewar Ready for AI&T in Tucson#
Level: 4
Due: 2018-10-17
Completed: 2019-06-30
Warning
No description available
COMC-060203-30028: COMP: C_FDR - Pathfinder#
Level: 4
Due: 2018-11-07
Completed: 2018-10-26
Warning
No description available
COMC-0620-4000: Corner Rafts Pre-Ship Acceptance#
Level: 3
Due: 2018-11-20
Completed: 2019-07-31
Warning
No description available
COMC-0620-4300: Cryostat+FPA Pre-Integration Acceptance#
Level: 3
Due: 2018-11-20
Completed: 2023-05-31
Warning
No description available
COMC-060200-20520: Base Facility Data Center Building + Utilities Ready#
Level: 4
Due: 2018-11-23
Completed: 2020-12-31
Warning
No description available
COMC-0620-2040: Base Facility Inspection Complete#
Level: 3
Due: 2018-11-23
Completed: 2018-11-05
Warning
No description available
COMC-060200-20100: Camera Facility Fiber Optic Lines Ready#
Level: 4
Due: 2018-11-28
Completed: 2021-10-29
Warning
No description available
COMC-060202-50200: COMP: C_PDR - Transport Container#
Level: Undefined
Due: 2018-12-17
Completed: 2019-03-07
Warning
No description available
COMC-0620-4700: Full Filter Complement Acceptance#
Level: 3
Due: 2019-01-09
Completed: 2022-01-31
Warning
No description available
COMC-0620-3200: Filter Mechanism Pre-Ship Acceptance#
Level: 3
Due: 2019-01-31
Completed: 2019-09-30
Warning
No description available
SUMMIT-2992: AVAIL: Refrigeration Pathfinder to ship#
Level: 4
Due: 2019-02-19
Completed: 2020-01-31
Warning
No description available
COMC-0620-3600: L3 Pre-Ship Acceptance#
Level: 3
Due: 2019-03-22
Completed: 2019-10-18
Warning
No description available
COMC-0620-4600: L1L2 Pre-Ship Acceptance#
Level: 3
Due: 2019-03-22
Completed: 2019-09-16
Warning
No description available
COMC-0620-0540: TS M1M3 Pre-Ship Acceptance#
Level: 3
Due: 2019-04-05
Completed: 2019-04-03
Warning
No description available
COMC-060200-20505: ComCam Dewar & Imaging System Ready for AI&T at Slac#
Level: 4
Due: 2019-04-09
Completed: 2019-05-31
Warning
No description available
COMC-060200-20400: Camera Staging Area Utilities Ready#
Level: 4
Due: 2019-05-01
Completed: 2019-05-01
Warning
No description available
COMC-060200-20200: Camera Facility Refrigeration Lines Ready#
Level: 4
Due: 2019-05-07
Completed: 2023-05-31
Warning
No description available
COMC-060200-20050: Summit Facility Camera Utility Room Ready#
Level: 4
Due: 2019-05-08
Completed: 2019-05-08
Warning
No description available
COMC-060200-20500: Summit Facility Clean Room Ready#
Level: 4
Due: 2019-05-09
Completed: 2019-05-08
Warning
No description available
COMC-060200-20300: Summit Facility White Room ready#
Level: 4
Due: 2019-05-09
Completed: 2019-05-08
Warning
No description available
COMC-06020201-1000: MIE: NEED: Filter Changer in Tucson#
Level: Undefined
Due: 2019-06-01
Completed: 2019-06-01
Warning
No description available
SITCOM-93: EAS Version 3 (construction tracking) ready to start#
Level: 4
Due: 2019-06-28
Completed: 2024-10-31
Warning
No description available
SUMMIT-2994: NEED: MIE Chile (TMA) Compressors#
Level: 3
Due: 2019-07-09
Completed: 2020-01-31
Warning
No description available
COMC-0620-3900: Shutter Pre-Integration Acceptance#
Level: 3
Due: 2019-07-18
Completed: 2020-02-21
Warning
No description available
COMC-060200-20030: Dome Installation Substantial Completion#
Level: 4
Due: 2019-08-22
Completed: 2019-11-19
Warning
No description available
COMC-060202-50450: COMP: C_FDR - Transport Container#
Level: Undefined
Due: 2019-09-05
Completed: 2023-12-01
Warning
No description available
COMC-060202-21110: Camera Hexapod/Rotator Ready for Integration#
Level: 4
Due: 2019-09-27
Completed: 2019-07-31
Warning
No description available
SIM-M2: UW Team FY19 Year End#
Level: 4
Due: 2019-09-30
Completed: 2019-09-30
Warning
No description available
COMC-060200-20810: Camera Cart1 + Integrator1 + CCW ready for ComCam#
Level: 4
Due: 2019-10-28
Completed: 2019-11-22
Warning
No description available
COMC-06020200-1100: Commissioning Readiness Review Complete#
Level: 4
Due: 2019-11-07
Completed: 2023-05-31
Warning
No description available
SUMMIT-2993: NEED: Refrigeration Pathfinder on summit#
Level: 4
Due: 2019-11-26
Completed: 2020-09-30
Warning
No description available
SITCOM-101: EAS version 5 installed (main telescope)#
Level: 4
Due: 2020-01-02
Completion pending
Warning
No description available
COMC-060200-20780: Auxiliary Telescope + Spectrograph Ready#
Level: 4
Due: 2020-01-21
Completed: 2019-04-12
Warning
No description available
SUMMIT-3008: AVAIL: White Room Refrigeration System Ready for LSSTCam#
Level: 3
Due: 2020-03-25
Completed: 2022-03-04
Warning
No description available
SUMMIT-3009: AVAIL: Pathfinder for ComCam#
Level: 3
Due: 2020-03-25
Completed: 2020-11-30
Warning
No description available
COMC-060202-50750: COMP: C_FDR - Transport Container#
Level: Undefined
Due: 2020-03-30
Completed: 2023-02-01
Warning
No description available
COMC-060200-10000: Start of On-Sky Data from Auxiliary Telescope#
Level: 4
Due: 2020-04-01
Completed: 2020-04-01
Warning
No description available
SUMMIT-2965: COMP: Camera Summit facility Ready for Use#
Level: 3
Due: 2020-04-01
Completed: 2020-04-01
Warning
No description available
COMC-060200-20750: ComCam arrives at summit#
Level: 4
Due: 2020-05-13
Completed: 2020-11-16
Warning
No description available
COMC-0620-0020: DMS Base Center Approved for System I&T#
Level: 3
Due: 2020-05-13
Completed: 2020-02-28
Warning
No description available
COMC-0620-2080: Summit Commissioning Cluster Test & Verficiation#
Level: 4
Due: 2020-05-14
Completed: 2024-04-15
Warning
No description available
COMC-0620-2090: Com. Cluster R8.1 Pre-Commissioning Acceptance#
Level: 3
Due: 2020-05-14
Completed: 2024-04-15
Warning
No description available
COMC-060200-20920: TMA Ready to Start Early System AI&T#
Level: 4
Due: 2020-06-10
Completed: 2020-06-10
Warning
No description available
SITCOM-89: ComCam + PathFinder installed on the cart Assembly at Level 3#
Level: 4
Due: 2020-06-17
Completed: 2021-08-31
Warning
No description available
NCSA-000: Start NCSA FY20 Services#
Level: 4
Due: 2020-07-30
Completed: 2020-07-30
Warning
No description available
SITCOM-88: Camera cart ready for ComCam#
Level: 4
Due: 2020-08-06
Completed: 2021-08-31
Warning
No description available
COMC-0620-2065: Base - Archive Network Functional 100 Gbps#
Level: 3
Due: 2020-12-29
Completed: 2024-10-04
Warning
No description available
SITCOM-91: Camera cart is fully assembled and tested#
Level: 4
Due: 2021-08-31
Completed: 2021-08-31
Warning
No description available
SUMMIT-3010: NEED: Access to TMA Refrigeration Lines#
Level: 3
Due: 2021-09-30
Completed: 2022-04-29
Warning
No description available
COMC-060200-20760: TCS w/WFS Available on Summit#
Level: 4
Due: 2021-10-29
Completed: 2023-05-31
Warning
No description available
SITCOM-90: ComCam + PF ready for on cart installation#
Level: 4
Due: 2021-12-30
Completed: 2021-12-30
Warning
No description available
SUMMIT-2955-500: Ready for ComCam - Refrigeration Tubing#
Level: Undefined
Due: 2022-02-07
Completed: 2021-11-30
Warning
No description available
SITCOM-95: Level 7th ready to receive the Camera cart Assembly#
Level: 4
Due: 2022-03-07
Completed: 2024-06-25
Warning
No description available
SITCOM-117: EAS fully integrated#
Level: 4
Due: 2022-03-31
Completion pending
Warning
No description available
COMC-060200-20965: Early System AI&T Complete#
Level: 4
Due: 2022-05-31
Completed: 2025-02-28
Warning
No description available
SITCOM-96: Computing Infrastructure in Place#
Level: 4
Due: 2022-05-31
Completed: 2024-10-01
Warning
No description available
SITCOM-112: Commissioning Compute Cluster fully configured and ready for general SIT-Com use#
Level: 4
Due: 2022-05-31
Completed: 2023-05-31
Warning
No description available
COMC-060200-20700: TMA Final Tests Start#
Level: 3
Due: 2022-06-06
Completed: 2024-03-29
Warning
No description available
COMC-0620-1100: Telescope Approved for System I&T#
Level: 3
Due: 2022-06-06
Completed: 2024-10-03
Warning
No description available
COMC-0620-0840: TMA Pre-Commissioning Acceptance#
Level: 3
Due: 2022-06-06
Completed: 2023-05-31
Warning
No description available
SITCOM-94: Level 3 System Spread integrations activities done#
Level: 4
Due: 2022-07-13
Completed: 2023-05-31
Warning
No description available
SUMMIT-2983: COMP: ComCam re-Verification Complete#
Level: 3
Due: 2022-07-13
Completed: 2020-11-15
Warning
No description available
SITCOM-100: M1M3 cell + Surrogate ready for installation on the TMA#
Level: 4
Due: 2023-04-17
Completed: 2023-06-15
Warning
No description available
SITCOM-108: Level-3 is ready for the M1M3 surrogate to glass transition#
Level: 4
Due: 2023-04-24
Completed: 2023-04-28
Warning
No description available
COMC-06020200-0800: Start Commissioning Readiness Review Preparations#
Level: 4
Due: 2023-05-01
Completed: 2023-05-01
Warning
No description available
COMC-0620-2240: Base-Archive Network Full BW (100 Gbps)#
Level: 3
Due: 2023-05-01
Completed: 2023-05-01
Warning
No description available
COMC-NR-606290(12): Shipping Frame Ready for Camera#
Level: Undefined
Due: 2023-05-22
Completed: 2023-05-22
Warning
No description available
SITCOM-106: Initial integrated tests on TMA complete#
Level: 4
Due: 2023-06-02
Completed: 2023-05-31
Warning
No description available
SITCOM-98: T&S Milestone: TMA Contract Complete#
Level: 4
Due: 2023-06-02
Completed: 2023-05-31
Warning
No description available
SITCOM-92: Camera support asmy w/ComCam+PF+Int#1+CCW Installed on Telescope#
Level: 4
Due: 2023-07-03
Completed: 2022-12-01
Warning
No description available
SUMMIT-3013: NEED: Pathfinder in ComCam on TMA#
Level: 3
Due: 2023-07-03
Completed: 2023-06-30
Warning
No description available
COMC-060200-20800: Telescope 3-Mirror Testing Starts#
Level: Undefined
Due: 2023-07-05
Completed: 2024-10-24
Warning
No description available
SITCOM-99: M1M3 cell + surrogate installed and verified on the TMA#
Level: 4
Due: 2023-07-17
Completed: 2024-03-29
Warning
No description available
SITCOM-102: TMA safe for transition to M1M3 glass mirror#
Level: 4
Due: 2023-07-19
Completed: 2024-09-30
Warning
No description available
SITCOM-120: Calibration Pipeline fully implemented#
Level: 4
Due: 2023-08-18
Completed: 2024-11-29
Warning
No description available
SITCOM-118: AuxTel ready for on-sky characterisation#
Level: 4
Due: 2023-08-18
Completed: 2023-05-31
Warning
No description available
SITCOM-97: M1M3 cell+Surrogate Dynamic Testing on TMA done#
Level: 4
Due: 2023-08-30
Completed: 2024-03-29
Warning
No description available
SUMMIT-2990: COMP: Calibration Telescope Ready for Operations#
Level: 3
Due: 2023-08-31
Completed: 2024-08-30
Warning
No description available
COMC-NR-606380(17): NEED: Hillman Rollers and Procedure#
Level: Undefined
Due: 2023-09-15
Completed: 2025-05-01
Warning
No description available
COMC-NR-700000(023): Camera Ready for Shipping#
Level: Undefined
Due: 2023-09-27
Completed: 2024-05-13
Warning
No description available
COMC-NR-700600(100): Camera Support Hardware & Fixtures Ready for Shipping#
Level: Undefined
Due: 2023-09-28
Completed: 2024-05-13
Warning
No description available
SITCOM-103: M2 fit check successful#
Level: 4
Due: 2023-09-28
Completed: 2023-09-15
Warning
No description available
COMC-NR-700500(066): Camera Spares Ready for Shipping#
Level: Undefined
Due: 2023-10-06
Completed: 2024-05-13
Warning
No description available
SITCOM-105: ComCam + PF re-Installed on TMA#
Level: 4
Due: 2023-10-06
Completed: 2024-08-19
Warning
No description available
COMC-0620-0940: Mirror Integration Complete#
Level: 3
Due: 2023-10-19
Completed: 2024-04-30
Warning
No description available
SUMMIT-2975: LSSTCam Pre-Ship Acceptance#
Level: 3
Due: 2023-10-20
Completed: 2024-04-06
Warning
No description available
COMC-0620-6300: Camera Pre-Ship Acceptance#
Level: 3
Due: 2023-10-20
Completed: 2024-04-06
Warning
No description available
SUMMIT-2976: LSSTCam Received @ Summit#
Level: 2
Due: 2023-11-06
Completed: 2024-05-16
Warning
No description available
SUMMIT-3055: COMP: L1/L2 recevied at summit#
Level: 3
Due: 2023-11-06
Completed: 2024-05-16
Warning
No description available
COMC-0620-6500: Camera Received @ Summit#
Level: 2
Due: 2023-11-14
Completed: 2024-05-16
Warning
No description available
SUMMIT-3023: COMP: TMA Refrigeration Tests Complete#
Level: 3
Due: 2023-12-27
Completed: 2024-11-01
Warning
No description available
COMC-NR-606560(36): Filter Exchange Spares Ready for Shipping#
Level: Undefined
Due: 2024-04-01
Completed: 2024-04-01
Warning
No description available
SITCOM-127: M2 coating decision#
Level: 4
Due: 2024-04-25
Completed: 2023-10-01
Warning
No description available
SITCOM-104: M2 Glass installed on Cell#
Level: 4
Due: 2024-04-25
Completed: 2024-07-08
Warning
No description available
COMC-060200-20930: Camera Ready for Full System AI&T#
Level: 4
Due: 2024-04-30
Completed: 2024-12-06
Warning
No description available
SUMMIT-3056: COMP: Camera Reverification Complete#
Level: 3
Due: 2024-04-30
Completed: 2024-12-06
Warning
No description available
SITCOM-125: LSSTCam reverification complete#
Level: 4
Due: 2024-04-30
Completed: 2024-12-06
Warning
No description available
COMC-NR-720000(075): L1-L2 Container Ready for Shipping#
Level: Undefined
Due: 2024-05-13
Completed: 2024-05-13
Warning
No description available
COMC-NR-720100(082): Shutter Equipment Ready for Shipping#
Level: Undefined
Due: 2024-05-13
Completed: 2024-05-13
Warning
No description available
COMC-NR-720200(87): FES Support Hardware Ready for Shipping#
Level: Undefined
Due: 2024-05-13
Completed: 2024-05-13
Warning
No description available
COMC-NR-606530(30): Shutter #2 Ready for Shipping#
Level: Undefined
Due: 2024-05-13
Completed: 2024-05-13
Warning
No description available
COMC-NR-606590(45): Filters Ready for Shipping#
Level: Undefined
Due: 2024-05-13
Completed: 2024-05-13
Warning
No description available
COMC-NR-606620(58): Cryo Cabinets Ready for Shipping#
Level: Undefined
Due: 2024-05-13
Completed: 2024-05-13
Warning
No description available
COMC-NR-606650(65): Chiller #1 Ready for Shipping#
Level: Undefined
Due: 2024-05-13
Completed: 2024-05-13
Warning
No description available
COMC-NR-701100(110): Camera And Equipment at SFO#
Level: Undefined
Due: 2024-05-14
Completed: 2024-05-14
Warning
No description available
COMC-NR-701600(111): LSST Camera at Santiago Airport#
Level: Undefined
Due: 2024-05-15
Completed: 2024-05-15
Warning
No description available
SITCOM-109: M1M3 Mirror Coating completed#
Level: 4
Due: 2024-05-15
Completed: 2024-04-30
Warning
No description available
COMC-060200-20970: Ready to Start Full System AI&T#
Level: 4
Due: 2024-05-21
Completed: 2025-02-28
Warning
No description available
SITCOM-110: M1M3 installed on the TMA#
Level: 4
Due: 2024-06-12
Completed: 2024-10-04
Warning
No description available
SUMMIT-Oct24-150: START: Reinstall ComCam on TMA#
Level: Undefined
Due: 2024-08-05
Completed: 2024-08-05
Warning
No description available
COMC-060200-20770: Global Interlock System Ready#
Level: 4
Due: 2024-08-20
Completed: 2025-04-25
Warning
No description available
COMC-060200-10210: Start of LSSTCam re-Verification#
Level: 4
Due: 2024-08-30
Completed: 2024-08-30
Warning
No description available
SITCOM-111: In-Dome Calibration Hardware Ready for On-Sky Operations#
Level: 4
Due: 2024-09-03
Completed: 2025-05-30
Warning
No description available
SUMMIT-Oct24-160: ComCam Reinstalled on TMA#
Level: Undefined
Due: 2024-09-06
Completed: 2024-08-19
Warning
No description available
SITCOM-114: All Data Management 1a Priority Requirements Functionally Demonstrated#
Level: 4
Due: 2024-09-09
Completion pending
Warning
No description available
COMC-0642-9999: COMP: DMS- Integration Complete#
Level: 4
Due: 2024-10-11
Completed: 2024-12-12
Warning
No description available
SUMMIT-Oct24-170: START: ComCam First Photon#
Level: Undefined
Due: 2024-10-25
Completed: 2024-10-25
Warning
No description available
SITCOM-116: Initial Optical testing on TMA complete#
Level: 4
Due: 2024-11-21
Completion pending
Warning
No description available
4: Start Saddle Stand Prep#
Level: Undefined
Due: 2024-12-09
Completed: 2024-12-09
Warning
No description available
SUMMIT-Oct24-180: COMP: ComCam on sky complete#
Level: Undefined
Due: 2024-12-12
Completed: 2024-12-12
Warning
No description available
6: ComCam in High Bay#
Level: Undefined
Due: 2024-12-20
Completed: 2024-12-20
Warning
No description available
5: Start Shipping Container Prep#
Level: Undefined
Due: 2024-12-23
Completed: 2024-12-23
Warning
No description available
7: SLAC Staff Return from Holidays#
Level: Undefined
Due: 2025-01-06
Completed: 2025-01-06
Warning
No description available
SITCOM-123: LSSTCam Installed on TMA#
Level: 4
Due: 2025-02-19
Completed: 2025-03-06
Warning
No description available
SITCOM-115: SIT-Com activities with ComCam Complete#
Level: Undefined
Due: 2025-02-20
Completed: 2024-12-31
Warning
No description available
8: LSSTCam on Top End Ready for TMA Integration#
Level: Undefined
Due: 2025-03-04
Completed: 2025-03-04
Warning
No description available
55: Rotate LSSTCam at 0 Degrees#
Level: Undefined
Due: 2025-03-20
Completed: 2025-03-20
Warning
No description available
66: CCDs on & Cryo Plate at Operating Temp#
Level: Undefined
Due: 2025-04-01
Completed: 2025-04-01
Warning
No description available
51: Ion Pumps On#
Level: Undefined
Due: 2025-04-01
Completed: 2025-04-01
Warning
No description available
New1135: LSSTCam Cold#
Level: 4
Due: 2025-04-02
Completed: 2025-03-21
Warning
No description available
81: Ready for TMA Balancing#
Level: Undefined
Due: 2025-04-04
Completed: 2025-04-04
Warning
No description available
SITCOM-XXX: Camera Ready for Engineering Punchlist Resolution#
Level: 4
Due: 2025-04-15
Completed: 2025-03-31
Warning
No description available
SITCOM-122: LSSTCam Ready for On Sky (First Photon)#
Level: 4
Due: 2025-04-22
Completed: 2025-04-14
Warning
No description available
COMC-060200-10300: Start of On-Sky & Calibration Data with LSSTCam#
Level: 4
Due: 2025-05-01
Completed: 2025-05-01
Warning
No description available
New1165: Telescope Aligned#
Level: 4
Due: 2025-05-01
Completed: 2025-04-16
Warning
No description available
New1110: Full focal plane readout complete#
Level: 4
Due: 2025-05-08
Completed: 2025-03-28
Warning
No description available
COMC-060200-20960: DMS Ready for Full system AI&T#
Level: 4
Due: 2025-05-29
Completion pending
Warning
No description available
SITCOM-119: Ops rehearsal for data release processing #3#
Level: 4
Due: 2025-05-29
Completion pending
Warning
No description available
SITCOM-121: System First Light with LSSTCam#
Level: 4
Due: 2025-05-29
Completion pending
Warning
No description available
COMC-060204-1000: Operational lookup tables for AOS complete#
Level: 4
Due: 2025-06-19
Completion pending
Warning
No description available
SITCOM-126: Engineering tests with LSSTCam complete#
Level: 4
Due: 2025-07-03
Completion pending
Warning
No description available
COMC-060200-10500: Start of Science Verification Science Validations#
Level: 4
Due: 2025-07-04
Completion pending
Warning
No description available
COMC-0620-9000: Archive Center Ready for System I&T at SLAC#
Level: 3
Due: 2025-07-04
Completed: 2025-04-30
Warning
No description available
SUMMIT-3082: COMP: LSSTCam-Tel Integration Complete#
Level: 3
Due: 2025-07-04
Completion pending
Warning
No description available
SUMMIT-3077: COMP: LSSTCam Ready for Bulk Data Production#
Level: 3
Due: 2025-07-04
Completion pending
Warning
No description available
COMC-0653-1000: COMP: Science Validation 1 Data Release Complete#
Level: 3
Due: 2025-09-11
Completion pending
Warning
No description available
COMC-0654-1000: COMP: Calibration Products Production Verified#
Level: 3
Due: 2025-09-11
Completion pending
Warning
No description available
COMC-0654-1070: COMP: Data Release Production Verified#
Level: 3
Due: 2025-09-11
Completion pending
Warning
No description available
COMC-0654-0430: COMP: Science Validation Surveys Complete#
Level: 3
Due: 2025-09-11
Completion pending
Warning
No description available
SITCOM-129: Science Verification Complete#
Level: 4
Due: 2025-09-18
Completion pending
Warning
No description available
SITCOM-130: Operation Readiness Review Complete#
Level: 4
Due: 2025-09-18
Completion pending
Warning
No description available