Provenance¶
This document was generated based on the contents of the lsst-dm/milestones repository, version ba7b3e73, dated 2022-12-09. This corresponds to the status recorded in the project controls system for October 2022.
Summary¶
The SITCOM Subsystem is currently tracking 198 milestones: 2 at Level 1, 2 at Level 2, 94 at Level 3, and 92 at Level 4. 8 have no level defined. Of these, 91 have been completed. Of the incomplete milestones, 39 are late relative to the baseline schedule, while the remainder are scheduled for the future.
Currently overdue milestones¶
Overdue SIT milestones
SITCOM-107: DELETE Engineering First Light w/ComCam [Due 2022-10-03]
SITCOM-100: M1M3 cell + Surrogate ready for installation on the TMA [Due 2022-11-16]
SITCOM-103: M2 fit check successful [Due 2022-10-24]
SITCOM-104: M2 Glass installed on Cell [Due 2022-10-03]
SITCOM-106: Initial integrated tests on TMA complete [Due 2022-10-03]
SITCOM-108: Level-3 is ready for the M1M3 surrogate to glass transition [Due 2022-11-23]
SITCOM-109: M1M3 Mirror Coating completed [Due 2022-10-03]
SITCOM-117: EAS fully integrated [Due 2022-10-03]
SITCOM-127: M2 coating decision [Due 2022-10-03]
SITCOM-94: Level 3 System Spread integrations activities done [Due 2022-10-26]
SITCOM-96: Computing Infrastructure in Place [Due 2022-10-03]
SITCOM-115: DELETE - SIT-Com activities with ComCam Complete [Due 2022-10-03]
SITCOM-118: AuxTel ready for on-sky characterisation [Due 2022-11-23]
SITCOM-120: Calibration Pipeline fully implemented [Due 2022-11-23]
SITCOM-112: Commissioning Compute Cluster fully configured and ready for general SIT-Com use [Due 2022-10-03]
SITCOM-116: Optical testing on TMA complete [Due 2022-10-03]
Overdue COM milestones
COMC-0030: Start Early Integration and Test [Due 2022-11-17]
COMC-0864: Telescope Top End Interface Ready for ComCam Integration [Due 2022-11-17]
COMC-1064: ComCam Ready at Summit [Due 2022-10-27]
COMC-0100: DELETE Begin ComCam On-Sky Use [Due 2022-10-03]
COMC-0620-0800: Start In-Situ TMA Testing [Due 2022-11-17]
COMC-0620-2150: Start Base Com. Cluster Test & Verification [Due 2022-10-03]
COMC-060200-10100: DELETE Start of On-Sky & Calibration Data with ComCam [Due 2022-10-03]
COMC-060200-20200: Camera Facility Refrigeration Lines Ready [Due 2022-10-03]
COMC-060200-20760: TCS w/WFS Available on Summit [Due 2022-10-03]
COMC-060200-20790: DELETE ComCam Ready to Start Early System AI&T [Due 2022-10-03]
COMC-060200-20965: Early System AI&T Complete [Due 2022-10-21]
COMC-0620-0840: TMA Pre-Commissioning Acceptance [Due 2022-11-17]
COMC-0620-1100: Telescope Approved for System I&T [Due 2022-11-17]
COMC-0620-2080: Base Com. Cluster Test & Verficiation [Due 2022-10-03]
COMC-0620-2090: Com. Cluster R8.1 Pre-Commissioning Acceptance [Due 2022-10-03]
COMC-0620-2240: Base-Archive Network Full BW (100 Gbps) [Due 2022-10-03]
COMC-0620-4300: Cryostat+FPA Pre-Integration Acceptance [Due 2022-10-03]
COMC-060202-50450: COMP: C_FDR - Transport Container [Due 2022-10-17]
COMC-060202-50750: COMP: C_FDR - Transport Container [Due 2022-10-03]
COMC-06020200-0800: Start Commissioning Readiness Review Preparations [Due 2022-10-10]
COMC-06020200-1100: Commissioning Readiness Review Complete [Due 2022-11-23]
Overdue SUM milestones
SUMMIT-3041: DELETE - COMP: ComCam Ready for Bulk Data Production [Due 2022-10-03]
SUMMIT-3047: DELETE - COMP: Engineering Tests w/ComCam Complete [Due 2022-10-03]
Milestones by due date¶
Due in November 2024¶
COMC-2164: Commissioning Complete
SITCOM-129: Science Verification Complete
COMC-0653-1000: COMP: Science Validation 1 Data Release Complete
COMC-0654-1000: COMP: Calibration Products Production Verified
COMC-0654-1070: COMP: Data Release Production Verified
COMC-0654-0430: Mini-Survey 2 Complete
SITCOM-130: Operation Readiness Review Complete
Due in October 2024¶
No milestones due.
Due in September 2024¶
No milestones due.
Due in August 2024¶
COMC-0140: Start SV Data Collection
COMC-060200-10500: Start of Science Verification Science Validations
SUMMIT-3082: COMP: LSSTCam-Tel Integration Complete
SUMMIT-3077: COMP: LSSTCam Ready for Bulk Data Production
SITCOM-126: Engineering tests with LSSTCam complete
Due in July 2024¶
COMC-1664: DMS Archive Center Complete at SLAC
SITCOM-119: Ops rehearsal for data release processing #3
COMC-0620-9000: Archive Center Ready for System I&T at SLAC
SITCOM-121: System First Light with LSSTCam
COMC-060204-1000: Operational lookup tables for AOS complete
Due in June 2024¶
No milestones due.
Due in May 2024¶
New1165: Telescope Aligned
Due in April 2024¶
COMC-060200-10300: Start of On-Sky & Calibration Data with LSSTCam
SITCOM-111: In-Dome Calibration Hardware Ready for On-Sky Operations
SITCOM-122: LSSTCam Ready for On Sky
New1110: Full focal plane readout complete
COMC-0642-9999: COMP: DMS- Integration Complete
Due in March 2024¶
COMC-1141: 3-mirrorTelescope Ready for Optical Testing
COMC-0020: On-Sky Testing Begins w/Science Camera
COMC-060200-20800: Telescope 3-Mirror Testing Starts
COMC-060200-20960: DMS Ready for Full system AI&T
SITCOM-110: M1M3 installed on the TMA
COMC-0620-0940: Mirror Integration Complete
SITCOM-XXX: Camera Ready for Engineering Punchlist Resolution
New1135: LSSTCam Cold
SITCOM-114: All Data Management 1a Priority Requirements Functionally Demonstrated
Due in February 2024¶
COMC-0010: Camera In-Situ Calibration Begins
SITCOM-123: LSSTCam Installed on TMA
Due in January 2024¶
COMC-060200-20770: Global Interlock System Ready
Due in December 2023¶
COMC-0130: Camera Ready for System Integration
COMC-0240: Begin Full system Integration
COMC-060200-20970: Ready to Start Full System AI&T
COMC-060200-20930: Camera Ready for Full System AI&T
SUMMIT-3056: COMP: Camera Reverification Complete
SITCOM-125: LSSTCam reverification complete
Due in November 2023¶
No milestones due.
Due in October 2023¶
No milestones due.
Due in September 2023¶
COMC-060200-10210: Start of LSSTCam re-Verification
Due in August 2023¶
No milestones due.
Due in July 2023¶
SUMMIT-3023: COMP: TMA Refrigeration Tests Complete
SITCOM-105: ComCam + PF re-Installed on TMA
Due in June 2023¶
SITCOM-124: Camera Arrives at Summit Facility
SUMMIT-2976: LSSTCam Received @ Summit
SITCOM-101: EAS version 5 installed (main telescope)
COMC-0620-6500: Camera Received @ Summit
SUMMIT-3055: COMP: L1/L2 recevied at summit
Due in May 2023¶
COMC-0005: Pre-Ship Camera Accepted
SUMMIT-2975: LSSTCam Pre-Ship Acceptance
SITCOM-97: M1M3 cell+Surrogate Dynamic Testing on TMA done
COMC-0620-6300: Camera Pre-Ship Acceptance
Due in April 2023¶
No milestones due.
Due in March 2023¶
SITCOM-102: TMA safe for transition to M1M3 glass mirror
SITCOM-99: M1M3 cell + surrogate installed and verified on the TMA
SITCOM-93: EAS Version 3 (construction tracking) ready to start
SUMMIT-3013: NEED: Pathfinder in ComCam on TMA
Due in February 2023¶
COMC-2264: Calibration Telescope Ready for Operations
COMC-1464: Start Photometric Calibration Tests
COMC-060200-20920: TMA Ready to Start Early System AI&T
SUMMIT-2990: COMP: Calibration Telescope Ready for Operations
Due in January 2023¶
SITCOM-98: T&S Milestone: TMA Contract Complete
Due in December 2022¶
COMC-0028: Base - Archive Network Verified
COMC-060200-20700: TMA Final Tests Start
SITCOM-92: Camera support asmy w/ComCam+PF+Int#1+CCW Installed on Telescope
SITCOM-95: Level 7th ready to receive the Camera cart Assembly
COMC-0620-2065: Base - Archive Network Functional 100 Gbps
SUMMIT-2955-500: Ready for ComCam - Refrigeration Tubing
Due in November 2022¶
COMC-0030: Start Early Integration and Test
COMC-0864: Telescope Top End Interface Ready for ComCam Integration
COMC-0620-0800: Start In-Situ TMA Testing
COMC-06020200-1100: Commissioning Readiness Review Complete
SITCOM-108: Level-3 is ready for the M1M3 surrogate to glass transition
SITCOM-100: M1M3 cell + Surrogate ready for installation on the TMA
COMC-0620-1100: Telescope Approved for System I&T
COMC-0620-0840: TMA Pre-Commissioning Acceptance
SITCOM-120: Calibration Pipeline fully implemented
SITCOM-118: AuxTel ready for on-sky characterisation
Due in October 2022¶
COMC-1064: ComCam Ready at Summit
COMC-0100: DELETE Begin ComCam On-Sky Use
SITCOM-107: DELETE Engineering First Light w/ComCam
COMC-0620-2150: Start Base Com. Cluster Test & Verification
COMC-06020200-0800: Start Commissioning Readiness Review Preparations
COMC-060202-50450: COMP: C_FDR - Transport Container
COMC-060202-50750: COMP: C_FDR - Transport Container
COMC-060200-10100: DELETE Start of On-Sky & Calibration Data with ComCam
COMC-060200-20200: Camera Facility Refrigeration Lines Ready
COMC-060200-20790: DELETE ComCam Ready to Start Early System AI&T
COMC-060200-20760: TCS w/WFS Available on Summit
COMC-060200-20965: Early System AI&T Complete
SITCOM-127: M2 coating decision
SITCOM-117: EAS fully integrated
SITCOM-109: M1M3 Mirror Coating completed
SITCOM-106: Initial integrated tests on TMA complete
SITCOM-104: M2 Glass installed on Cell
SITCOM-103: M2 fit check successful
SITCOM-96: Computing Infrastructure in Place
SITCOM-94: Level 3 System Spread integrations activities done
COMC-0620-2240: Base-Archive Network Full BW (100 Gbps)
COMC-0620-2080: Base Com. Cluster Test & Verficiation
COMC-0620-2090: Com. Cluster R8.1 Pre-Commissioning Acceptance
COMC-0620-4300: Cryostat+FPA Pre-Integration Acceptance
SUMMIT-3047: DELETE - COMP: Engineering Tests w/ComCam Complete
SUMMIT-3041: DELETE - COMP: ComCam Ready for Bulk Data Production
SITCOM-115: DELETE - SIT-Com activities with ComCam Complete
SITCOM-116: Optical testing on TMA complete
SITCOM-112: Commissioning Compute Cluster fully configured and ready for general SIT-Com use
Due in September 2022¶
No milestones due.
Due in August 2022¶
No milestones due.
Due in July 2022¶
SUMMIT-2983: COMP: ComCam re-Verification Complete
Due in June 2022¶
No milestones due.
Due in May 2022¶
No milestones due.
Due in April 2022¶
No milestones due.
Due in March 2022¶
No milestones due.
Due in February 2022¶
No milestones due.
Due in January 2022¶
No milestones due.
Due in December 2021¶
SITCOM-90: ComCam + PF ready for on cart installation
Due in November 2021¶
No milestones due.
Due in October 2021¶
No milestones due.
Due in September 2021¶
SUMMIT-3010: NEED: Access to TMA Refrigeration Lines
Due in August 2021¶
SITCOM-91: Camera cart is fully assembled and tested
Due in July 2021¶
No milestones due.
Due in June 2021¶
No milestones due.
Due in May 2021¶
No milestones due.
Due in April 2021¶
No milestones due.
Due in March 2021¶
COMC-2864: ComCam Ready for Onsite Systems Test
Due in February 2021¶
No milestones due.
Due in January 2021¶
No milestones due.
Due in December 2020¶
No milestones due.
Due in November 2020¶
No milestones due.
Due in October 2020¶
No milestones due.
Due in September 2020¶
No milestones due.
Due in August 2020¶
SITCOM-88: Camera cart ready for ComCam
Due in July 2020¶
NCSA-000: Start NCSA FY20 Services
Due in June 2020¶
SITCOM-89: ComCam + PathFinder installed on the cart Assembly at Level 3
Due in May 2020¶
COMC-0964: Start ComCam Integration on Summit
COMC-1564: DMS Base Center Complete
COMC-060200-20750: ComCam arrives at summit
COMC-0620-0020: DMS Base Center Approved for System I&T
Due in April 2020¶
SUMMIT-2965: COMP: Camera Summit facility Ready for Use
COMC-060200-10000: Start of On-Sky Data from Auxiliary Telescope
Due in March 2020¶
A5860: Start of Tucson Integration Tests w/ComCam
SUMMIT-3008: AVAIL: White Room Refrigeration System Ready for LSSTCam
SUMMIT-3009: AVAIL: Pathfinder for ComCam
Due in February 2020¶
COMC-1164: Commissioning Data Processing Cluster Ready for ComCam Use
Due in January 2020¶
COMC-060200-20780: Auxiliary Telescope + Spectrograph Ready
Due in December 2019¶
No milestones due.
Due in November 2019¶
SUMMIT-2993: NEED: Refrigeration Pathfinder on summit
Due in October 2019¶
COMC-060200-20810: Camera Cart1 + Integrator1 + CCW ready for ComCam
Due in September 2019¶
SIM-M2: UW Team FY19 Year End
COMC-060202-21110: Camera Hexapod/Rotator Ready for Integration
Due in August 2019¶
COMC-060200-20030: Dome Installation Substantial Completion
Due in July 2019¶
COMC-0564: ComCam Ready for System Tests
COMC-2464: ComCam Ready for Verification in Tucson
COMC-0620-3900: Shutter Pre-Integration Acceptance
SUMMIT-2994: NEED: MIE Chile (TMA) Compressors
Due in June 2019¶
COMC-0620-0900: Start Mirror Coating & Integration
COMC-0620-4400: Start L1L2 Testing & Verification
COMC-06020201-1000: MIE: NEED: Filter Changer in Tucson
Due in May 2019¶
COMC-0021: Mountain-Base Network Verified
COMC-0620-2000: Start Base Facility Inspection
COMC-0620-4100: Start Integrated Cryostat Testing
COMC-060200-20050: Summit Facility Camera Utility Room Ready
COMC-060200-20500: Summit Facility Clean Room Ready
COMC-060200-20400: Camera Staging Area Utilities Ready
COMC-060200-20300: Summit Facility White Room ready
Due in April 2019¶
COMC-0364: ComCam Dewar Assmebly Ready for Integration
COMC-2364: Coating Facility Ready for Operations
COMC-0620-3000: Start Filter Mechanism Testing
COMC-0620-3700: Start Shutter Testing
COMC-060200-20505: ComCam Dewar & Imaging System Ready for AI&T at Slac
COMC-0620-0540: TS M1M3 Pre-Ship Acceptance
Due in March 2019¶
COMC-0620-3400: Start L3 Assembly Test
COMC-0620-3600: L3 Pre-Ship Acceptance
COMC-0620-4600: L1L2 Pre-Ship Acceptance
Due in February 2019¶
SUMMIT-2992: AVAIL: Refrigeration Pathfinder to ship
Due in January 2019¶
COMC-0620-3200: Filter Mechanism Pre-Ship Acceptance
COMC-0620-4700: Full Filter Complement Acceptance
Due in December 2018¶
COMC-060202-50200: COMP: C_PDR - Transport Container
Due in November 2018¶
COMC-0620-0500: Start M1M3+Cell Integration at SOML
COMC-060200-20100: Camera Facility Fiber Optic Lines Ready
COMC-060200-20520: Base Facility Data Center Building + Utilities Ready
COMC-0620-2040: Base Facility Inspection Complete
COMC-0620-4000: Corner Rafts Pre-Ship Acceptance
COMC-060203-30028: COMP: C_FDR - Pathfinder
Due in October 2018¶
COMC-0620-0300: Start M2+Cell Integrated Optical Tests
COMC-06020201-2200: MIE: PSR ComCam deliverables
COMC-060200-20510: ComCam Dewar Ready for AI&T in Tucson
COMC-060200-20710: OCS Available on Summit
Due in September 2018¶
SIM-M1: UW Sims FY18 Year End
COMC-0620-2070: Base Infrastructure Pre-Ship Acceptance
Due in August 2018¶
COMC-060200-20020: Summit Control Room Available
COMC-060200-20025: Engineering Facility Database Functional
COMC-0620-0640: Coating Chamber Pre-Ship Acceptance
Due in July 2018¶
COMC-0464: ComCam Optics & Filters Ready for Integration in tucson
COMC-060203-30018: COMP: C_PDR - Pathfinder
Due in June 2018¶
COMC-0620-0600: Start Coating System testing at Vendor
COMC-060200-20010: Summit Facility Computer Room Available
Due in May 2018¶
COMC-06020201-3180: COMP: C_CR - 2018 Commissioning Review
COMC-0620-0340: M2 Pre-Ship Acceptance
Due in April 2018¶
COMC-060200-20000: Summit Network Available
COMC-060203-30008: COMP: C_CDR - Pathfinder
Due in March 2018¶
COMC-06020201-3100: COMP: C_TCR - 2018 Technical Commissioning Review
COMC-0620-2050: MTN-Base Network Full BW (2 x 100 Gbps)
Due in February 2018¶
COMC-0620-0700: Start Summit Facility Inspection
COMC-0620-0240: Rotator/Hexapopd Pre-Ship Acceptance
Due in January 2018¶
COMC-0620-3300: 1st Production Science Raft Acceptance
Due in December 2017¶
COMC-0620-0440: TMA Pre-Ship Acceptance
Due in November 2017¶
COMC-0620-0740: Summit Facility Inspection Complete
Due in October 2017¶
No milestones due.
Due in September 2017¶
No milestones due.
Due in August 2017¶
No milestones due.
Due in July 2017¶
No milestones due.
Due in June 2017¶
COMC-0620-0200: Start Rotator/Hexapod Testing at Vendor
COMC-06020201-1200: MIE: NEED: Shutter at SLAC
Due in May 2017¶
No milestones due.
Due in April 2017¶
COMC-06020200-0700: Commissioning Baseline Accepted
Due in March 2017¶
No milestones due.
Due in February 2017¶
No milestones due.
Due in January 2017¶
COMC-06020200-0500: Commissioning PDR Complete
Due in December 2016¶
No milestones due.
Due in November 2016¶
COMC-0620-0400: Start TMA Test at Vendor
Due in October 2016¶
No milestones due.
Due in September 2016¶
No milestones due.
Due in August 2016¶
No milestones due.
Due in July 2016¶
No milestones due.
Due in June 2016¶
COMC-0620-0100: Start Dome Testing at Vendor
Due in May 2016¶
No milestones due.
Due in April 2016¶
No milestones due.
Due in March 2016¶
No milestones due.
Due in February 2016¶
No milestones due.
Due in January 2016¶
No milestones due.
Due in December 2015¶
No milestones due.
Due in November 2015¶
No milestones due.
Due in October 2015¶
No milestones due.
Due in September 2015¶
Due in August 2015¶
No milestones due.
Due in July 2015¶
No milestones due.
Due in June 2015¶
COMC-2310: LSE-76 Infrastructure between Summit Fac. & DM - Phase 3, DM Milestone
Due in May 2015¶
No milestones due.
Due in April 2015¶
No milestones due.
Due in March 2015¶
No milestones due.
Due in February 2015¶
No milestones due.
Due in January 2015¶
COMC-1205: LSE-140 Aux Instrum ICD between DM & T&S, Phase 3, DM Milestone
Milestones by WBS¶
06C.00: SITCOM Management Level 2 Milestones¶
COMC-1205: LSE-140 Aux Instrum ICD between DM & T&S, Phase 3, DM Milestone¶
Level: 3
Due: 2015-01-13
Completed: 2019-07-31
Warning
No description available
COMC-2310: LSE-76 Infrastructure between Summit Fac. & DM - Phase 3, DM Milestone¶
Level: 3
Due: 2015-06-02
Completed: 2019-07-31
Warning
No description available
COMC-2330: LSE-76 Infrastructure between Summit Fac. & DM - Phase 3, T&S Milestone¶
Level: 3
Due: 2015-09-02
Completed: 2017-09-30
Warning
No description available
COMC-1110: LSE-132 Infrastructure between Summit Fac. & OCS - Phase 3, T&S Milestone¶
Level: 3
Due: 2015-09-02
Completed: 2019-04-15
Warning
No description available
COMC-0620-0100: Start Dome Testing at Vendor¶
Level: 3
Due: 2016-06-06
Completed: 2016-06-06
Warning
No description available
COMC-0620-0400: Start TMA Test at Vendor¶
Level: 3
Due: 2016-11-01
Completed: 2016-11-01
Warning
No description available
COMC-0620-0200: Start Rotator/Hexapod Testing at Vendor¶
Level: 3
Due: 2017-06-28
Completed: 2017-06-28
Warning
No description available
COMC-0620-0700: Start Summit Facility Inspection¶
Level: 3
Due: 2018-02-28
Completed: 2018-02-28
Warning
No description available
COMC-0620-0600: Start Coating System testing at Vendor¶
Level: 3
Due: 2018-06-11
Completed: 2018-06-11
Warning
No description available
COMC-0620-0300: Start M2+Cell Integrated Optical Tests¶
Level: 3
Due: 2018-10-01
Completed: 2018-10-01
Warning
No description available
COMC-0620-0500: Start M1M3+Cell Integration at SOML¶
Level: 3
Due: 2018-11-15
Completed: 2018-11-15
Warning
No description available
COMC-0620-3400: Start L3 Assembly Test¶
Level: 3
Due: 2019-03-11
Completed: 2019-03-11
Warning
No description available
COMC-0364: ComCam Dewar Assmebly Ready for Integration¶
Level: 3
Due: 2019-04-09
Completed: 2019-06-01
Warning
No description available
COMC-0620-3000: Start Filter Mechanism Testing¶
Level: 3
Due: 2019-04-12
Completed: 2019-04-12
Warning
No description available
COMC-0620-3700: Start Shutter Testing¶
Level: 3
Due: 2019-04-19
Completed: 2019-04-19
Warning
No description available
COMC-2364: Coating Facility Ready for Operations¶
Level: 3
Due: 2019-04-24
Completed: 2019-06-03
Warning
No description available
COMC-0620-4100: Start Integrated Cryostat Testing¶
Level: 3
Due: 2019-05-01
Completed: 2019-05-01
Warning
No description available
COMC-0620-2000: Start Base Facility Inspection¶
Level: 3
Due: 2019-05-03
Completed: 2019-05-03
Warning
No description available
COMC-0021: Mountain-Base Network Verified¶
Level: 3
Due: 2019-05-10
Completed: 2019-05-10
Warning
No description available
COMC-0620-0900: Start Mirror Coating & Integration¶
Level: 3
Due: 2019-06-03
Completed: 2019-06-03
Warning
No description available
COMC-0620-4400: Start L1L2 Testing & Verification¶
Level: 3
Due: 2019-06-12
Completed: 2019-06-12
Warning
No description available
COMC-2464: ComCam Ready for Verification in Tucson¶
Level: 3
Due: 2019-07-01
Completed: 2019-07-01
Warning
No description available
COMC-0564: ComCam Ready for System Tests¶
Level: 3
Due: 2019-07-18
Completed: 2019-07-31
Warning
No description available
COMC-1164: Commissioning Data Processing Cluster Ready for ComCam Use¶
Level: 3
Due: 2020-02-28
Completed: 2020-02-28
Warning
No description available
A5860: Start of Tucson Integration Tests w/ComCam¶
Level: 4
Due: 2020-03-31
Completed: 2020-03-31
Warning
No description available
COMC-1564: DMS Base Center Complete¶
Level: 3
Due: 2020-05-13
Completed: 2020-02-28
Warning
No description available
COMC-0964: Start ComCam Integration on Summit¶
Level: 3
Due: 2020-05-20
Completed: 2021-03-31
Warning
No description available
COMC-2864: ComCam Ready for Onsite Systems Test¶
Level: 3
Due: 2021-03-31
Completed: 2021-03-31
Warning
No description available
COMC-0100: DELETE Begin ComCam On-Sky Use¶
Level: 3
Due: 2022-10-03
Completion pending
Warning
No description available
SITCOM-107: DELETE Engineering First Light w/ComCam¶
Level: 1
Due: 2022-10-03
Completion pending
Warning
No description available
COMC-0620-2150: Start Base Com. Cluster Test & Verification¶
Level: 3
Due: 2022-10-03
Completion pending
Warning
No description available
COMC-1064: ComCam Ready at Summit¶
Level: 3
Due: 2022-10-27
Completion pending
Warning
No description available
COMC-0030: Start Early Integration and Test¶
Level: 3
Due: 2022-11-17
Completion pending
Warning
No description available
COMC-0864: Telescope Top End Interface Ready for ComCam Integration¶
Level: 3
Due: 2022-11-17
Completion pending
Warning
No description available
COMC-0620-0800: Start In-Situ TMA Testing¶
Level: 3
Due: 2022-11-17
Completion pending
Warning
No description available
COMC-0028: Base - Archive Network Verified¶
Level: 3
Due: 2022-12-29
Completion pending
Warning
No description available
COMC-1464: Start Photometric Calibration Tests¶
Level: 3
Due: 2023-02-10
Completion pending
Warning
No description available
COMC-2264: Calibration Telescope Ready for Operations¶
Level: 3
Due: 2023-02-22
Completion pending
Warning
No description available
COMC-0005: Pre-Ship Camera Accepted¶
Level: 3
Due: 2023-05-12
Completion pending
Warning
No description available
SITCOM-124: Camera Arrives at Summit Facility¶
Level: 4
Due: 2023-06-07
Completion pending
Warning
No description available
COMC-0130: Camera Ready for System Integration¶
Level: 3
Due: 2023-12-05
Completion pending
Warning
No description available
COMC-0240: Begin Full system Integration¶
Level: 3
Due: 2023-12-06
Completion pending
Warning
No description available
COMC-0010: Camera In-Situ Calibration Begins¶
Level: 3
Due: 2024-02-12
Completion pending
Warning
No description available
COMC-0020: On-Sky Testing Begins w/Science Camera¶
Level: 3
Due: 2024-03-04
Completion pending
Warning
No description available
COMC-1141: 3-mirrorTelescope Ready for Optical Testing¶
Level: 3
Due: 2024-03-11
Completion pending
Warning
No description available
COMC-1664: DMS Archive Center Complete at SLAC¶
Level: 3
Due: 2024-07-09
Completion pending
Warning
No description available
COMC-0140: Start SV Data Collection¶
Level: 3
Due: 2024-08-14
Completion pending
Warning
No description available
COMC-2164: Commissioning Complete¶
Level: 3
Due: 2024-11-11
Completion pending
Warning
No description available
06C.02: Commissioning¶
COMC-06020200-0500: Commissioning PDR Complete¶
Level: 4
Due: 2017-01-27
Completed: 2017-01-27
Warning
No description available
COMC-06020200-0700: Commissioning Baseline Accepted¶
Level: 4
Due: 2017-04-14
Completed: 2017-12-01
Warning
No description available
COMC-06020201-1200: MIE: NEED: Shutter at SLAC¶
Level: Undefined
Due: 2017-06-10
Completed: 2017-06-10
Warning
No description available
COMC-0620-0740: Summit Facility Inspection Complete¶
Level: 3
Due: 2017-11-13
Completed: 2019-01-01
Warning
No description available
COMC-0620-0440: TMA Pre-Ship Acceptance¶
Level: 3
Due: 2017-12-01
Completed: 2018-11-19
Warning
No description available
COMC-0620-3300: 1st Production Science Raft Acceptance¶
Level: 3
Due: 2018-01-12
Completed: 2017-05-26
Warning
No description available
COMC-0620-0240: Rotator/Hexapopd Pre-Ship Acceptance¶
Level: 3
Due: 2018-02-21
Completed: 2019-01-01
Warning
No description available
COMC-06020201-3100: COMP: C_TCR - 2018 Technical Commissioning Review¶
Level: 3
Due: 2018-03-05
Completed: 2018-02-01
Warning
No description available
COMC-0620-2050: MTN-Base Network Full BW (2 x 100 Gbps)¶
Level: 3
Due: 2018-03-27
Completed: 2018-04-02
Warning
No description available
COMC-060200-20000: Summit Network Available¶
Level: 4
Due: 2018-04-12
Completed: 2018-10-01
Warning
No description available
COMC-060203-30008: COMP: C_CDR - Pathfinder¶
Level: 4
Due: 2018-04-19
Completed: 2018-01-18
Warning
No description available
COMC-06020201-3180: COMP: C_CR - 2018 Commissioning Review¶
Level: 3
Due: 2018-05-07
Completed: 2018-07-31
Warning
No description available
COMC-0620-0340: M2 Pre-Ship Acceptance¶
Level: 3
Due: 2018-05-11
Completed: 2018-10-31
Warning
No description available
COMC-060200-20010: Summit Facility Computer Room Available¶
Level: 4
Due: 2018-06-07
Completed: 2018-10-01
Warning
No description available
COMC-0464: ComCam Optics & Filters Ready for Integration in tucson¶
Level: 1
Due: 2018-07-09
Completed: 2019-02-01
Warning
No description available
COMC-060203-30018: COMP: C_PDR - Pathfinder¶
Level: 4
Due: 2018-07-30
Completed: 2018-07-31
Warning
No description available
COMC-060200-20025: Engineering Facility Database Functional¶
Level: 4
Due: 2018-08-06
Completed: 2018-11-04
Warning
No description available
COMC-0620-0640: Coating Chamber Pre-Ship Acceptance¶
Level: 3
Due: 2018-08-13
Completed: 2018-08-14
Warning
No description available
COMC-060200-20020: Summit Control Room Available¶
Level: 4
Due: 2018-08-20
Completed: 2018-10-01
Warning
No description available
COMC-0620-2070: Base Infrastructure Pre-Ship Acceptance¶
Level: 3
Due: 2018-09-26
Completed: 2018-04-11
Warning
No description available
SIM-M1: UW Sims FY18 Year End¶
Level: 4
Due: 2018-09-28
Completed: 2018-10-01
Warning
No description available
COMC-06020201-2200: MIE: PSR ComCam deliverables¶
Level: Undefined
Due: 2018-10-01
Completed: 2019-05-31
Warning
No description available
COMC-060200-20710: OCS Available on Summit¶
Level: 4
Due: 2018-10-12
Completed: 2019-11-09
Warning
No description available
COMC-060200-20510: ComCam Dewar Ready for AI&T in Tucson¶
Level: 4
Due: 2018-10-17
Completed: 2019-06-30
Warning
No description available
COMC-060203-30028: COMP: C_FDR - Pathfinder¶
Level: 4
Due: 2018-11-07
Completed: 2018-10-26
Warning
No description available
COMC-0620-4000: Corner Rafts Pre-Ship Acceptance¶
Level: 3
Due: 2018-11-20
Completed: 2019-07-31
Warning
No description available
COMC-060200-20520: Base Facility Data Center Building + Utilities Ready¶
Level: 4
Due: 2018-11-23
Completed: 2020-12-31
Warning
No description available
COMC-0620-2040: Base Facility Inspection Complete¶
Level: 3
Due: 2018-11-23
Completed: 2018-11-05
Warning
No description available
COMC-060200-20100: Camera Facility Fiber Optic Lines Ready¶
Level: 4
Due: 2018-11-28
Completed: 2021-10-29
Warning
No description available
COMC-060202-50200: COMP: C_PDR - Transport Container¶
Level: Undefined
Due: 2018-12-17
Completed: 2019-03-07
Warning
No description available
COMC-0620-4700: Full Filter Complement Acceptance¶
Level: 3
Due: 2019-01-09
Completed: 2022-01-31
Warning
No description available
COMC-0620-3200: Filter Mechanism Pre-Ship Acceptance¶
Level: 3
Due: 2019-01-31
Completed: 2019-09-30
Warning
No description available
SUMMIT-2992: AVAIL: Refrigeration Pathfinder to ship¶
Level: 4
Due: 2019-02-19
Completed: 2020-01-31
Warning
No description available
COMC-0620-3600: L3 Pre-Ship Acceptance¶
Level: 3
Due: 2019-03-22
Completed: 2019-10-18
Warning
No description available
COMC-0620-4600: L1L2 Pre-Ship Acceptance¶
Level: 3
Due: 2019-03-22
Completed: 2019-09-16
Warning
No description available
COMC-0620-0540: TS M1M3 Pre-Ship Acceptance¶
Level: 3
Due: 2019-04-05
Completed: 2019-04-03
Warning
No description available
COMC-060200-20505: ComCam Dewar & Imaging System Ready for AI&T at Slac¶
Level: 4
Due: 2019-04-09
Completed: 2019-05-31
Warning
No description available
COMC-060200-20400: Camera Staging Area Utilities Ready¶
Level: 4
Due: 2019-05-01
Completed: 2019-05-01
Warning
No description available
COMC-060200-20050: Summit Facility Camera Utility Room Ready¶
Level: 4
Due: 2019-05-08
Completed: 2019-05-08
Warning
No description available
COMC-060200-20500: Summit Facility Clean Room Ready¶
Level: 4
Due: 2019-05-09
Completed: 2019-05-08
Warning
No description available
COMC-060200-20300: Summit Facility White Room ready¶
Level: 4
Due: 2019-05-09
Completed: 2019-05-08
Warning
No description available
COMC-06020201-1000: MIE: NEED: Filter Changer in Tucson¶
Level: Undefined
Due: 2019-06-01
Completed: 2019-06-01
Warning
No description available
SUMMIT-2994: NEED: MIE Chile (TMA) Compressors¶
Level: 3
Due: 2019-07-09
Completed: 2020-01-31
Warning
No description available
COMC-0620-3900: Shutter Pre-Integration Acceptance¶
Level: 3
Due: 2019-07-18
Completed: 2020-02-21
Warning
No description available
COMC-060200-20030: Dome Installation Substantial Completion¶
Level: 4
Due: 2019-08-22
Completed: 2019-11-19
Warning
No description available
COMC-060202-21110: Camera Hexapod/Rotator Ready for Integration¶
Level: 4
Due: 2019-09-27
Completed: 2019-07-31
Warning
No description available
SIM-M2: UW Team FY19 Year End¶
Level: 4
Due: 2019-09-30
Completed: 2019-09-30
Warning
No description available
COMC-060200-20810: Camera Cart1 + Integrator1 + CCW ready for ComCam¶
Level: 4
Due: 2019-10-28
Completed: 2019-11-22
Warning
No description available
SUMMIT-2993: NEED: Refrigeration Pathfinder on summit¶
Level: 4
Due: 2019-11-26
Completed: 2020-09-30
Warning
No description available
COMC-060200-20780: Auxiliary Telescope + Spectrograph Ready¶
Level: 4
Due: 2020-01-21
Completed: 2019-04-12
Warning
No description available
SUMMIT-3008: AVAIL: White Room Refrigeration System Ready for LSSTCam¶
Level: 3
Due: 2020-03-25
Completed: 2022-03-04
Warning
No description available
SUMMIT-3009: AVAIL: Pathfinder for ComCam¶
Level: 3
Due: 2020-03-25
Completed: 2020-11-30
Warning
No description available
COMC-060200-10000: Start of On-Sky Data from Auxiliary Telescope¶
Level: 4
Due: 2020-04-01
Completed: 2020-04-01
Warning
No description available
SUMMIT-2965: COMP: Camera Summit facility Ready for Use¶
Level: 3
Due: 2020-04-01
Completed: 2020-04-01
Warning
No description available
COMC-0620-0020: DMS Base Center Approved for System I&T¶
Level: 3
Due: 2020-05-13
Completed: 2020-02-28
Warning
No description available
COMC-060200-20750: ComCam arrives at summit¶
Level: 4
Due: 2020-05-20
Completed: 2020-11-16
Warning
No description available
SITCOM-89: ComCam + PathFinder installed on the cart Assembly at Level 3¶
Level: 4
Due: 2020-06-24
Completed: 2021-08-31
Warning
No description available
NCSA-000: Start NCSA FY20 Services¶
Level: 4
Due: 2020-07-30
Completed: 2020-07-30
Warning
No description available
SITCOM-88: Camera cart ready for ComCam¶
Level: 4
Due: 2020-08-13
Completed: 2021-08-31
Warning
No description available
SITCOM-91: Camera cart is fully assembled and tested¶
Level: 4
Due: 2021-08-31
Completed: 2021-08-31
Warning
No description available
SUMMIT-3010: NEED: Access to TMA Refrigeration Lines¶
Level: 3
Due: 2021-09-30
Completed: 2022-04-29
Warning
No description available
SITCOM-90: ComCam + PF ready for on cart installation¶
Level: 4
Due: 2021-12-30
Completed: 2021-12-30
Warning
No description available
SUMMIT-2983: COMP: ComCam re-Verification Complete¶
Level: 3
Due: 2022-07-20
Completed: 2020-11-15
Warning
No description available
COMC-060202-50750: COMP: C_FDR - Transport Container¶
Level: Undefined
Due: 2022-10-03
Completion pending
Warning
No description available
COMC-060200-10100: DELETE Start of On-Sky & Calibration Data with ComCam¶
Level: 4
Due: 2022-10-03
Completion pending
Warning
No description available
COMC-060200-20200: Camera Facility Refrigeration Lines Ready¶
Level: 4
Due: 2022-10-03
Completion pending
Warning
No description available
COMC-060200-20790: DELETE ComCam Ready to Start Early System AI&T¶
Level: 4
Due: 2022-10-03
Completion pending
Warning
No description available
COMC-060200-20760: TCS w/WFS Available on Summit¶
Level: 4
Due: 2022-10-03
Completion pending
Warning
No description available
SITCOM-127: M2 coating decision¶
Level: 4
Due: 2022-10-03
Completion pending
Warning
No description available
SITCOM-117: EAS fully integrated¶
Level: 4
Due: 2022-10-03
Completion pending
Warning
No description available
SITCOM-109: M1M3 Mirror Coating completed¶
Level: 4
Due: 2022-10-03
Completion pending
Warning
No description available
SITCOM-106: Initial integrated tests on TMA complete¶
Level: 4
Due: 2022-10-03
Completion pending
Warning
No description available
SITCOM-104: M2 Glass installed on Cell¶
Level: 4
Due: 2022-10-03
Completion pending
Warning
No description available
SITCOM-96: Computing Infrastructure in Place¶
Level: 4
Due: 2022-10-03
Completion pending
Warning
No description available
COMC-0620-2240: Base-Archive Network Full BW (100 Gbps)¶
Level: 3
Due: 2022-10-03
Completion pending
Warning
No description available
COMC-0620-2080: Base Com. Cluster Test & Verficiation¶
Level: 4
Due: 2022-10-03
Completion pending
Warning
No description available
COMC-0620-2090: Com. Cluster R8.1 Pre-Commissioning Acceptance¶
Level: 3
Due: 2022-10-03
Completion pending
Warning
No description available
COMC-0620-4300: Cryostat+FPA Pre-Integration Acceptance¶
Level: 3
Due: 2022-10-03
Completion pending
Warning
No description available
SUMMIT-3047: DELETE - COMP: Engineering Tests w/ComCam Complete¶
Level: 3
Due: 2022-10-03
Completion pending
Warning
No description available
SUMMIT-3041: DELETE - COMP: ComCam Ready for Bulk Data Production¶
Level: 3
Due: 2022-10-03
Completion pending
Warning
No description available
SITCOM-115: DELETE - SIT-Com activities with ComCam Complete¶
Level: 4
Due: 2022-10-03
Completion pending
Warning
No description available
SITCOM-116: Optical testing on TMA complete¶
Level: 4
Due: 2022-10-03
Completion pending
Warning
No description available
SITCOM-112: Commissioning Compute Cluster fully configured and ready for general SIT-Com use¶
Level: 4
Due: 2022-10-03
Completion pending
Warning
No description available
COMC-06020200-0800: Start Commissioning Readiness Review Preparations¶
Level: 4
Due: 2022-10-10
Completion pending
Warning
No description available
COMC-060202-50450: COMP: C_FDR - Transport Container¶
Level: Undefined
Due: 2022-10-17
Completion pending
Warning
No description available
COMC-060200-20965: Early System AI&T Complete¶
Level: 4
Due: 2022-10-21
Completion pending
Warning
No description available
SITCOM-103: M2 fit check successful¶
Level: 4
Due: 2022-10-24
Completion pending
Warning
No description available
SITCOM-94: Level 3 System Spread integrations activities done¶
Level: 4
Due: 2022-10-26
Completion pending
Warning
No description available
SITCOM-100: M1M3 cell + Surrogate ready for installation on the TMA¶
Level: 4
Due: 2022-11-16
Completion pending
Warning
No description available
COMC-0620-1100: Telescope Approved for System I&T¶
Level: 3
Due: 2022-11-17
Completion pending
Warning
No description available
COMC-0620-0840: TMA Pre-Commissioning Acceptance¶
Level: 3
Due: 2022-11-17
Completion pending
Warning
No description available
COMC-06020200-1100: Commissioning Readiness Review Complete¶
Level: 4
Due: 2022-11-23
Completion pending
Warning
No description available
SITCOM-108: Level-3 is ready for the M1M3 surrogate to glass transition¶
Level: 4
Due: 2022-11-23
Completion pending
Warning
No description available
SITCOM-120: Calibration Pipeline fully implemented¶
Level: 4
Due: 2022-11-23
Completion pending
Warning
No description available
SITCOM-118: AuxTel ready for on-sky characterisation¶
Level: 4
Due: 2022-11-23
Completion pending
Warning
No description available
COMC-060200-20700: TMA Final Tests Start¶
Level: 3
Due: 2022-12-28
Completion pending
Warning
No description available
SITCOM-92: Camera support asmy w/ComCam+PF+Int#1+CCW Installed on Telescope¶
Level: 4
Due: 2022-12-28
Completion pending
Warning
No description available
SITCOM-95: Level 7th ready to receive the Camera cart Assembly¶
Level: 4
Due: 2022-12-28
Completion pending
Warning
No description available
SUMMIT-2955-500: Ready for ComCam - Refrigeration Tubing¶
Level: Undefined
Due: 2022-12-28
Completion pending
Warning
No description available
COMC-0620-2065: Base - Archive Network Functional 100 Gbps¶
Level: 3
Due: 2022-12-29
Completion pending
Warning
No description available
SITCOM-98: T&S Milestone: TMA Contract Complete¶
Level: 4
Due: 2023-01-31
Completion pending
Warning
No description available
COMC-060200-20920: TMA Ready to Start Early System AI&T¶
Level: 4
Due: 2023-02-01
Completion pending
Warning
No description available
SUMMIT-2990: COMP: Calibration Telescope Ready for Operations¶
Level: 3
Due: 2023-02-22
Completion pending
Warning
No description available
SUMMIT-3013: NEED: Pathfinder in ComCam on TMA¶
Level: 3
Due: 2023-03-22
Completion pending
Warning
No description available
SITCOM-99: M1M3 cell + surrogate installed and verified on the TMA¶
Level: 4
Due: 2023-03-28
Completion pending
Warning
No description available
SITCOM-102: TMA safe for transition to M1M3 glass mirror¶
Level: 4
Due: 2023-03-30
Completion pending
Warning
No description available
SITCOM-93: EAS Version 3 (construction tracking) ready to start¶
Level: 4
Due: 2023-03-31
Completion pending
Warning
No description available
SITCOM-97: M1M3 cell+Surrogate Dynamic Testing on TMA done¶
Level: 4
Due: 2023-05-05
Completion pending
Warning
No description available
SUMMIT-2975: LSSTCam Pre-Ship Acceptance¶
Level: 3
Due: 2023-05-12
Completion pending
Warning
No description available
COMC-0620-6300: Camera Pre-Ship Acceptance¶
Level: 3
Due: 2023-05-12
Completion pending
Warning
No description available
SITCOM-101: EAS version 5 installed (main telescope)¶
Level: 4
Due: 2023-06-02
Completion pending
Warning
No description available
SUMMIT-2976: LSSTCam Received @ Summit¶
Level: 2
Due: 2023-06-07
Completion pending
Warning
No description available
COMC-0620-6500: Camera Received @ Summit¶
Level: 2
Due: 2023-06-07
Completion pending
Warning
No description available
SUMMIT-3055: COMP: L1/L2 recevied at summit¶
Level: 3
Due: 2023-06-07
Completion pending
Warning
No description available
SUMMIT-3023: COMP: TMA Refrigeration Tests Complete¶
Level: 3
Due: 2023-07-04
Completion pending
Warning
No description available
SITCOM-105: ComCam + PF re-Installed on TMA¶
Level: 4
Due: 2023-07-17
Completion pending
Warning
No description available
COMC-060200-10210: Start of LSSTCam re-Verification¶
Level: 4
Due: 2023-09-26
Completion pending
Warning
No description available
COMC-060200-20930: Camera Ready for Full System AI&T¶
Level: 4
Due: 2023-12-05
Completion pending
Warning
No description available
SUMMIT-3056: COMP: Camera Reverification Complete¶
Level: 3
Due: 2023-12-05
Completion pending
Warning
No description available
SITCOM-125: LSSTCam reverification complete¶
Level: 4
Due: 2023-12-05
Completion pending
Warning
No description available
COMC-060200-20970: Ready to Start Full System AI&T¶
Level: 4
Due: 2023-12-06
Completion pending
Warning
No description available
COMC-060200-20770: Global Interlock System Ready¶
Level: 4
Due: 2024-01-12
Completion pending
Warning
No description available
SITCOM-123: LSSTCam Installed on TMA¶
Level: 4
Due: 2024-02-09
Completion pending
Warning
No description available
SITCOM-110: M1M3 installed on the TMA¶
Level: 4
Due: 2024-03-11
Completion pending
Warning
No description available
COMC-0620-0940: Mirror Integration Complete¶
Level: 3
Due: 2024-03-11
Completion pending
Warning
No description available
COMC-060200-20800: Telescope 3-Mirror Testing Starts¶
Level: 4
Due: 2024-03-12
Completion pending
Warning
No description available
COMC-060200-20960: DMS Ready for Full system AI&T¶
Level: 4
Due: 2024-03-22
Completion pending
Warning
No description available
SITCOM-114: All Data Management 1a Priority Requirements Functionally Demonstrated¶
Level: 4
Due: 2024-03-22
Completion pending
Warning
No description available
SITCOM-XXX: Camera Ready for Engineering Punchlist Resolution¶
Level: 4
Due: 2024-03-29
Completion pending
Warning
No description available
New1135: LSSTCam Cold¶
Level: 4
Due: 2024-03-29
Completion pending
Warning
No description available
SITCOM-122: LSSTCam Ready for On Sky¶
Level: 4
Due: 2024-04-05
Completion pending
Warning
No description available
COMC-060200-10300: Start of On-Sky & Calibration Data with LSSTCam¶
Level: 4
Due: 2024-04-08
Completion pending
Warning
No description available
COMC-0642-9999: COMP: DMS- Integration Complete¶
Level: 4
Due: 2024-04-19
Completion pending
Warning
No description available
SITCOM-111: In-Dome Calibration Hardware Ready for On-Sky Operations¶
Level: 4
Due: 2024-04-22
Completion pending
Warning
No description available
New1110: Full focal plane readout complete¶
Level: 4
Due: 2024-04-23
Completion pending
Warning
No description available
New1165: Telescope Aligned¶
Level: 4
Due: 2024-05-07
Completion pending
Warning
No description available
SITCOM-119: Ops rehearsal for data release processing #3¶
Level: 4
Due: 2024-07-09
Completion pending
Warning
No description available
COMC-0620-9000: Archive Center Ready for System I&T at SLAC¶
Level: 3
Due: 2024-07-09
Completion pending
Warning
No description available
SITCOM-121: System First Light with LSSTCam¶
Level: 4
Due: 2024-07-09
Completion pending
Warning
No description available
COMC-060204-1000: Operational lookup tables for AOS complete¶
Level: Undefined
Due: 2024-07-30
Completion pending
Warning
No description available
SITCOM-126: Engineering tests with LSSTCam complete¶
Level: 4
Due: 2024-08-13
Completion pending
Warning
No description available
COMC-060200-10500: Start of Science Verification Science Validations¶
Level: 4
Due: 2024-08-14
Completion pending
Warning
No description available
SUMMIT-3082: COMP: LSSTCam-Tel Integration Complete¶
Level: 3
Due: 2024-08-14
Completion pending
Warning
No description available
SUMMIT-3077: COMP: LSSTCam Ready for Bulk Data Production¶
Level: 3
Due: 2024-08-14
Completion pending
Warning
No description available
COMC-0653-1000: COMP: Science Validation 1 Data Release Complete¶
Level: 3
Due: 2024-11-04
Completion pending
Warning
No description available
COMC-0654-1000: COMP: Calibration Products Production Verified¶
Level: 3
Due: 2024-11-04
Completion pending
Warning
No description available
COMC-0654-1070: COMP: Data Release Production Verified¶
Level: 3
Due: 2024-11-04
Completion pending
Warning
No description available
COMC-0654-0430: Mini-Survey 2 Complete¶
Level: 3
Due: 2024-11-04
Completion pending
Warning
No description available
SITCOM-129: Science Verification Complete¶
Level: 4
Due: 2024-11-11
Completion pending
Warning
No description available
SITCOM-130: Operation Readiness Review Complete¶
Level: 4
Due: 2024-11-11
Completion pending
Warning
No description available